CDFM Module 4 Exam questions with correct answers CDFM Module 4 Exam questions with correct answers CDFM Module 4 Exam questions with correct answers CDFM Module 4 Exam questions with correct answers CDFM Module 4 Exam questions with correct answers

Meer zien Lees minder
Instelling
CDFM
Vak
CDFM










Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
CDFM
Vak
CDFM

Documentinformatie

Geüpload op
8 januari 2026
Aantal pagina's
21
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

CDFM Module 4 Exam questions with
correct answers
What |are |Joint |Acquisition |Programs? |- |VERIFIED |ANSWER✔✔-Joint |Acquisition |Programs |is |any
|acqusition |system, |subsystem, |component, |or |technology |program |with |astrategy |that |includes

|funding |by |more |than |one |DoD |component |during |any |phase |of |a |system's |life |cycle.




Who |decides |to |place |programs |under |joint |acquisition |management? |- |VERIFIED |ANSWER✔✔-The
|MDA |decides |whether |to |place |programs |under |joint |management |and |designates |the |lead |executive

|DoD |component.




What |law |requires |an |analysis |of |potential |opportunities |of |international |cooperation? |- |VERIFIED
|ANSWER✔✔-10 |USC |2350a(e) |requires |international |cooperation |consideration |in |the |initial

|aquisition |strategy |for |a |program.




When |international |programs |may |be |established |in |the |defense |acqusition |program |- |VERIFIED
|ANSWER✔✔-Decision |to |include |international |partners |needs |to |be |included |during |development |of

|the |initial |capabilities |document |but |no |early |than |the |material |and |solution |analysis |phase.




When |is |Earned |Value |Management |(EVM) |implemented |- |VERIFIED |ANSWER✔✔-EVM |is |part |of
|program |management |. |It |ensures |that |cost |, |schedule |and |technical |aspects |of |the |contract |are |truly

|integrated.




In |what |type |of |contracts |EVM |is |required |- |VERIFIED |ANSWER✔✔-EVM |is |required |on |Cost, |and/or
|Incentive |contracts |valued |at |greater |than |$20M.




What |is |EVM? |- |VERIFIED |ANSWER✔✔-Earned |Value |Management |is |a |tool |that

1. |Relates |the |scope |of |the |work |to |its |associated |budgets |and |schedule.

2. |Measures |the |work |progress |in |objective |terms

3. |States |that |value |of |the |work |completed |in |dollars |and |other |measurable |units.

,What |are |EVM |techniques? |- |VERIFIED |ANSWER✔✔-Correlate |the |budgeted |cost |of |worked |scheduled
|with |the |budget |cost |of |work |performed |(BCWP)



1. |0/100 |Earned |Value |Technique

2. |Percent |Start/Percent |Finish |EV |Technique |(50/50) |(25/75) |(80/20)

3. |Percent |Complete

4. |Units |Completed

5. |Equivalent |Units



Describe |the |Percent |Start/Percent |Finish |EV |Technique |- |VERIFIED |ANSWER✔✔-Is |an |objective
|earned |value |technique |tied |to |the |start |and |completion |of |a |work |package |task, |often |referred |to |%

|assigned |to |the |start |and |finish |milestone |such |as |(50/50...)



Thsi |technique |tends |to |overstate |performance |in |the |first |half |of |the |period |of |performance |and
|uderstate |performance |in |the |last |half.




What |is |the |most |important |step |in |EVM |system? |- |VERIFIED |ANSWER✔✔-Is |the |establishment |of |the
|Performance |Measurement |Baseline |(PMB)or |the |Budgeted |Cost |of |Work |Schedule |(BCWS)




What |is |the |PMB |in |and |EVM? |- |VERIFIED |ANSWER✔✔-The |PMB |includes |the |undistributed |budget,
|all |summary |level |planning |package |budgets, |and |all |control |account |budgets. |It |does |not |include

|management |reserve.




What |is |the |final |step |of |the |PMB? |- |VERIFIED |ANSWER✔✔-Is |to |classify |work, |to |allocate |the |budget
|and |to |time |phase |the |control |account |work |package |budgets. |This |last |phase |is |calculate |BWCS




How |do |we |classify |work |packages |in |EVM? |- |VERIFIED |ANSWER✔✔-in |3 |categories, |Discrete,
|apportioned |effort, |and |level |of |effort.




Describe |the |realignment |of |the |PMB |- |VERIFIED |ANSWER✔✔-Rebaselining, |Replanning, |and
|Reprogramming




What |is |Reprogramming? |- |VERIFIED |ANSWER✔✔-Reprogramming |is |a |comprehensive |realignment |of
|the |remaining |performance |measurement |baseline |that |results |in |a |total |budget |and/or |total

, |schedule |that |exceeds |the |contractual |requirements. |It |is |the |process |that |results |in |an |Over-Target
|Baseline |or |OTB |and |an |Over-Target |Schedule |OTS.




Schedule |Performance |Index |(SPI) |formula |- |VERIFIED |ANSWER✔✔-SPI=BCWP/BCWS



Estimate |at |Completion |(EAC) |formula |- |VERIFIED |ANSWER✔✔-EAC=ACWP+[(BAC-
BCWP)/(Performance |Factor)]



EAC |Compsite |formula |- |VERIFIED |ANSWER✔✔-ACWPcum+[(BAC-BCWPcum)/(CPIcum*SPIcum)]

Upper |Value |(worst |case)



EVM |Terminology |- |VERIFIED |ANSWER✔✔-EAC=Estimate |at |Completion

BAC=Budget |at |Completion(current)

BCWS=Budget |Cost |of |Work |Scheduled |(current)

BWCP=Budget |Cost |of |Work |Performed |(earned |value)

ACWP=Actual |Cost |of |Work |Performed



What |is |the |Contractor |Cost |and |Software |Data |Reporting |(CSDR) |- |VERIFIED |ANSWER✔✔-The |CSDR
|system |involves |two |formal |contractor |reports, |the |COntractor |Cost |Data |Report |(CCDR) |and |the

|Software |Resources |Data |Report |(SRDR)




What |is |Contract |Performance |Report |(CPR) |- |VERIFIED |ANSWER✔✔-The |PM |should |obtain |from |the
|contractor |a |CPR |(DD |form |2734) |on |all |contracts |the |meet |or |exceed |EVMS |dollar |thresholds |and

|require |EVMS |compliance. |The |CPR |provides |contract |cost |and |schedule |performance |for |program

|mangement.




What |is |Contract |Funds |Status |Report |(CFSR) |- |VERIFIED |ANSWER✔✔-(DD |1586) |has |no |specific
|application |thresholds |but |PMs |should |evaluate |contracts |of |less |than |$1.3M. |FFP |contracts |should

|not |apply |the |CFSR |unless |unusual |circumnstances |dictate |funding |visibility.




What |is |Government |Contract |Quality |Assurance |(GCQA) |- |VERIFIED |ANSWER✔✔-DCMA |Q&A
|personnel |conducts |quality |assurance |as |identified |in |contract |administration |delegations |by |the |KO.

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Nursepasspro stuvia
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
16
Lid sinds
7 maanden
Aantal volgers
1
Documenten
1037
Laatst verkocht
1 week geleden

4,3

3 beoordelingen

5
2
4
0
3
1
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen