100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

General Contractor (Commercial) Certification QUESTION AND CORRECT ANSWERS (VERIFIED ANSWERS) PLUS RATIONALES 2026 Q&A INSTANT DOWNLOAD PDF

Beoordeling
-
Verkocht
-
Pagina's
36
Cijfer
A+
Geüpload op
07-01-2026
Geschreven in
2025/2026

General Contractor (Commercial) Certification QUESTION AND CORRECT ANSWERS (VERIFIED ANSWERS) PLUS RATIONALES 2026 Q&A INSTANT DOWNLOAD PDF

Instelling
General Contractor Certification
Vak
General Contractor Certification











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
General Contractor Certification
Vak
General Contractor Certification

Documentinformatie

Geüpload op
7 januari 2026
Aantal pagina's
36
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

General Contractor (Commercial)
Certification QUESTION AND CORRECT
ANSWERS (VERIFIED ANSWERS) PLUS
RATIONALES 2026 Q&A INSTANT
DOWNLOAD PDF

1. What is the primary purpose of a general contractor on a
commercial construction project?
A. To provide labor only
B. To manage and coordinate all aspects of construction
C. To design the building
D. To inspect electrical systems
Answer: B. To manage and coordinate all aspects of construction
Rationale: The general contractor oversees the entire construction
process, including subcontractors, schedules, budgets, and compliance
with codes.


2. Which document outlines the responsibilities of the owner,
contractor, and architect?
A. Construction schedule
B. Contract agreement
C. Building permit
D. Material specifications

,Answer: B. Contract agreement
Rationale: The contract agreement legally defines roles, responsibilities,
and obligations of all parties involved in the project.


3. What is the typical role of a subcontractor in commercial
construction?
A. Approve project financing
B. Perform specialized work under the general contractor
C. Oversee the entire construction project
D. Issue permits
Answer: B. Perform specialized work under the general contractor
Rationale: Subcontractors are hired for specific trades such as
plumbing, electrical, or HVAC under the management of the general
contractor.


4. Which of the following is a key component of a construction
schedule?
A. Payment terms
B. Milestones and deadlines
C. Material color options
D. Warranty duration
Answer: B. Milestones and deadlines
Rationale: Construction schedules outline start and finish dates for
project phases, critical for timely completion.

,5. What type of insurance is essential for a general contractor to
protect against job site injuries?
A. Life insurance
B. Workers’ compensation insurance
C. Vehicle insurance
D. Health insurance
Answer: B. Workers’ compensation insurance
Rationale: Workers’ compensation protects employees in case of injuries
sustained while working on the construction site.


6. What does the term “retainage” refer to in construction contracts?
A. Profit margin
B. Portion of payment withheld until project completion
C. Insurance premium
D. Overhead costs
Answer: B. Portion of payment withheld until project completion
Rationale: Retainage ensures the contractor completes the work
satisfactorily before receiving full payment.


7. When is a punch list typically created?
A. Before construction begins
B. During the design phase
C. Near the end of construction
D. After warranty period

, Answer: C. Near the end of construction
Rationale: A punch list identifies incomplete or deficient work to be
corrected before final project acceptance.


8. What is the purpose of a building permit?
A. To authorize demolition only
B. To ensure construction complies with local codes
C. To order materials
D. To hire subcontractors
Answer: B. To ensure construction complies with local codes
Rationale: Building permits verify that construction meets safety,
structural, and zoning regulations.


9. Which type of contract pays the contractor a fixed amount
regardless of actual costs?
A. Cost-plus contract
B. Lump-sum contract
C. Time and materials contract
D. Unit-price contract
Answer: B. Lump-sum contract
Rationale: A lump-sum contract sets a fixed total price, placing the risk
of cost overruns on the contractor.


10. What is the main purpose of construction site safety meetings?
A. To train subcontractors on scheduling
€20,94
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten

Maak kennis met de verkoper
Seller avatar
mrpass

Maak kennis met de verkoper

Seller avatar
mrpass Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
Nieuw op Stuvia
Lid sinds
1 maand
Aantal volgers
0
Documenten
804
Laatst verkocht
-

0,0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen