100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

BICSI Installer 1 Certification Exam 2025 All 60 Questions and Correct Answers (Already Graded A+) | Latest Version

Beoordeling
-
Verkocht
-
Pagina's
19
Cijfer
A+
Geüpload op
04-12-2025
Geschreven in
2025/2026

This comprehensive study guide contains all 60 questions with correct answers for the BICSI Installer 1 Certification Exam 2025, already graded A+ in the latest version. Covering all essential telecommunications installation topics including cable pulling, termination techniques, testing procedures, safety protocols, and industry standards for copper and fiber optic cabling systems.

Meer zien Lees minder
Instelling
BICSI Installer 1 Certification
Vak
BICSI Installer 1 Certification










Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
BICSI Installer 1 Certification
Vak
BICSI Installer 1 Certification

Documentinformatie

Geüpload op
4 december 2025
Aantal pagina's
19
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

BICSI INSTALLER 1 CERTIFICATION EXAM 2025
ALL 60 QUESTIONS AND CORRECT ANSWERS
(ALREADY GRADED A+) | LATEST VERSION
Introduction

This 2025 BICSI Installer 1 simulation presents 60 original exam-grade items that
mirror the current certification blueprint:

• Cabling installation practices

• Codes, standards, and regulations

• Safety procedures

• Copper and fiber-optic testing

• Telecommunications theory

• Bonding and grounding

• Pathways and spaces

All content is written for mastery-level preparation and aligns with the 2025 BICSI
ITSIMM, ANSI/TIA-568.4-D, and applicable NEC/CSA requirements. No question
duplicates proprietary BICSI material.



Question 1
When installing a 4-pair Category 6A UTP cable horizontally above a factory floor with
480 V motor drives, the minimum separation distance (no divider) per TIA-569-E is:
A. 300 mm
B. 600 mm
C. 1,000 mm
D. 50 mm

Answer: B. 600 mm
Solution: TIA-569-E Table 4.3 specifies 600 mm (24 in.) between communications
cables and power >300 V to <600 V when no physical barrier is used. 300 mm is for
power <300 V; 1,000 mm is not listed; 50 mm is for screened power within the same
tray.



Question 2
A 50/125 µm laser-optimized multimode fiber must support 40 GbE (40GBASE-SR4)
over 150 m. The highest OM rating acceptable is:


pg. 1

,A. OM2
B. OM3
C. OM4
D. OM5

Answer: C. OM4
Solution: OM4 is specified to 150 m for 40GBASE-SR4. OM3 only reaches 100 m; OM2 is
insufficient (≤50 m); OM5 supports the distance but is not the highest acceptable
rating—OM4 already meets the requirement.



Question 3
During a pull of 24-fiber indoor/outdoor cable, the tensile load gauge reads 800 N.
Manufacturer’s maximum pulling tension is 2,500 N. The correct action is:
A. Increase pulling speed to reduce friction heat
B. Continue; tension is within spec
C. Reduce pulling force to ≤600 N and use additional lubricant
D. Reverse the pull to redistribute stress

Answer: B. Continue; tension is within spec
Solution: 800 N < 2,500 N limit—no violation. Increasing speed (A) risks burn-
through; reducing to 600 N (C) is unnecessary; reversing (D) wastes time and may kink
cable.



Question 4
Which tool is primary for verifying proper blade depth when preparing 900 µm tight-
buffered fiber for mechanical splice?
A. Visual fault locator (VFL)
B. Fiber cleave inspection microscope
C. Buffer strip gauge
D. OTDR

Answer: C. Buffer strip gauge
Solution: The buffer strip gauge (or factory strip-length template) ensures correct
buffer removal without nicking fiber. Microscope (B) checks cleave quality; VFL (A)
checks continuity; OTDR (D) is for end-to-end characterization.



Question 5
A copper cable run between two buildings (different electrical services) exhibits 60 V AC
between shield and building ground. The first safety step is:
A. Isolate the shield at one end
B. Bond the shield to the main earthing bar immediately


pg. 2

, C. De-energize and verify absence of voltage before handling
D. Apply dielectric grease to the connector

Answer: C. De-energize and verify absence of voltage before handling
Solution: Treat as energized circuit—lock-out/tag-out first. Bonding (B) might create
arc flash; isolation (A) is corrective but not first safety action; grease (D) is irrelevant.



Question 6
The minimum cover depth for direct-buried communications cable under a residential
concrete driveway per NEC 2025 Table 300.5 is:
A. 300 mm (12 in.)
B. 450 mm (18 in.)
C. 600 mm (24 in.)
D. 100 mm (4 in.)

Answer: B. 450 mm (18 in.)
Solution: NEC 300.5 specifies 450 mm (18 in.) under driveways not subject to truck
traffic. 600 mm is for public streets; 300 mm is for yard areas without vehicles; 100 mm
is insufficient.



Question 7
A continuity test on a Cat 6 horizontal run shows 6.0 Ω end-to-end on conductor #4. The
maximum allowable per TIA-1152A is:
A. 5 Ω
B. 10 Ω
C. 25 Ω
D. 0.1 Ω

Answer: A. 5 Ω
Solution: TIA-1152A clause 6.2.2 sets 5 Ω maximum DC resistance for any 100 m
horizontal conductor. 10 Ω and 25 Ω are obsolete specs; 0.1 Ω is typical for patch cords
only.



Question 8
When fusion-splicing ribbon fiber, the most critical parameter monitored by the
splicer’s PAS (profile alignment system) is:
A. Core concentricity error
B. Cladding diameter mismatch
C. Fiber curl radius
D. Cleave angle deviation



pg. 3

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TutorAgness Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
10
Lid sinds
1 jaar
Aantal volgers
5
Documenten
436
Laatst verkocht
1 week geleden

4,5

2 beoordelingen

5
1
4
1
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Veelgestelde vragen