Ace your Massachusetts 1A Hoisting License Exam with this latest 2025–2026 Test Bank and Study Guide, featuring accurate questions and verified answers, all rated A for reliability and excellence. This comprehensive resource covers key areas, including crane operations, safety procedures, load management, and Massachusetts hoisting regulations. Each question mirrors real exam standards, providing clear explanations to enhance understanding and boost confidence. Perfect for candidates seeking a thorough, effective, and high-quality preparation for the Mass 1A Hoisting certification exam.

Meer zien Lees minder
Instelling
Hoisting
Vak
Hoisting











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Hoisting
Vak
Hoisting

Documentinformatie

Geüpload op
4 november 2025
Aantal pagina's
38
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

Mass 1A Hoisting Test Bank Guide
Study Guide Latest 2025-2026 Rated A
1% - ANSIf a crane is out of level by 1%, you can lose upto 50% capacity


125 pounds - ANSWeight of one cubic foot of soil


3300 pounds - ANSPounds weight of one cubic yard of soil


6.09 special requirements for Cranes: - ANSSpecial Requirements for
Cranes.
(a) Loading.
Material moving, handling or hoisting machinery shall be loaded in
accordance with the manufacturer's specifications. Manufacturers' load-
rating plates or
applicable load charts shall be kept in the cab of the crane in clear view of
the operator.
Rating plates or load charts for boom cranes shall clearly indicate the safe
load for maximum
and minimum positions of the boom and for at least two intermediate
positions. The
procedures applicable to the operation of the equipment, including
instructions,
recommended operating speeds, special hazard warnings, and operator's
manual, must be

,readily available in the cab at all times for use by the operator. Where rated
capacities are
available in the cab only in electronic form: In the event of a failure which
makes the rated
capacities inaccessible, the operator must immediately cease operations or
follow safe
shut-down procedures until the rated capacities (in electronic or other form)
are available
.
(b) Boom Stops. Devices to prevent the boom from falling over backward
shall be provided
on cranes. Cable boom stops by themselves shall not be considered as
adequate for this
purpose.


(c) Speed Controls and Stops. Hoisting machinery operating on rails, tracks
or trolleys shall
be equipped with speed controls and shall have positive stops or limiting
devices to prevent
overrunning safe limits.


(d) Equipment Modifications. Any modification made to hoisting machinery
shall maintain
at least the same factor of safety as the original designed equipment. A
record of the
differences between the unmodified machinery and the modified machinery
shall be

,maintained by the owner of the machinery and furnished to the Department
upon request.
All modifications shall be done with the manufacturer's written approval. If
the
manufacturer's writ


6.09 Special Requirements for Derricks - ANS(2) Special Requirements for
Derricks.
(a) Required Inspection. Guys, cable clamps and other rigging shall be
visually checked by
the operator at the beginning of each work day and before making any lifts
that are near the
capacity of the rig or as otherwise required by the manufacturer.


(b) Frequent checking by a duly licensed person of lead cables and mast
foot blocks shall
be performed to ensure that cables are not crossed or fouled. Lead line
blocks shall be
checked frequently to ensure that they are properly secured. Leads shall be
so arranged as
to minimize tripping hazards.


6.09 Special Requirements for Excavating Machines - ANS(5) Special
Requirements for Excavating Machines, Including Backhoes and Frontend
Loaders.

, (a) Dig Safe. Prior to any excavation, Dig Safe and other utilities not
covered by Dig Safe
must be notified. The operator must have a Dig Safe permit number, start
date, and time.


(b) Protection of Operator. Where the operator of an excavating machine
may be exposed
to the elements or overhead hazards, a suitable equipped cab for
protection against such
conditions shall be provided.


(c) Operation. Excavating machines shall be operated by a licensee,
temporary permit
holder, or an apprentice licensee under the direct supervision of a duly
licensed operator.
SAE hand signals shall be used with excavating machinery. No person
except the operating
crew or apprentice licensee operating under the direct supervision of a duly
licensed operator
shall be permitted on an excavating machine while it is in operation.


No person other than
the pitman and excavating crew shall be permitted to stand within the full
working radius of
an excavator or backhoe while the shovel or backhoe is in operation.


Excavating machinery
€13,16
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten

Maak kennis met de verkoper
Seller avatar
wilfredmburuUS

Maak kennis met de verkoper

Seller avatar
wilfredmburuUS Johns Hopkins University School Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
4
Lid sinds
1 jaar
Aantal volgers
0
Documenten
790
Laatst verkocht
3 dagen geleden
Grade A+ Assignments, Exams, Quizzes, and Homework

EXCELLENT ASSIGNMENT AND EXERCISES HELP & TUTORING, ALL KINDS OF QUIZS & EXAMS WITH A GUARANTEED GRADE A. I am an expert on major courses especially; Human Resource Management, Criminal Justice, Criminology, Nursing, Sociology, Data Science, Environmental Science, Management Leadership and Forensics ensuring quality work delivery. I maintain scholarly standards in all my work, ensuring students get the best from me. I assure you a GOOD GRADE if you will use my work.

Lees meer Lees minder
0,0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Veelgestelde vragen