ACCURATE ANSWERS
"dedicated" project manager correct answer role in life is to be a
project manager regardless of the operational needs of the business.
"dedicated" project manager correct answer role in life is to be a
project manager regardless of the operational needs of the business.
"working" project manager correct answer a functional manager
"working" project manager correct answer a functional manager
0-100 Rule correct answer Every task is marked as 0% completed until it
is finished, then marked as 100%
50-50 Rule correct answer Assigns 50% compete once activity is started,
and 100% upon completion. No in between, every task is marked with
either a 0%, 50%, or 100%
8 and 80 Rule correct answer a project manager should avoid
controlling tasks that take less than eight hours and should not let more
than two weeks go by without checking in
,8 and 80 Rule correct answer a project manager should avoid
controlling tasks that take less than eight hours and should not let more
than two weeks go by without checking in
8/80 rule correct answer do not assign anything that takes less than
eight hours so we allow resources sufficient work to occupy them and
we don't micromanage
AC correct answer Actual Cost
Total dollar value of costs to date, includes work and invoices already
paid as well as expenses that have been incurred but not invoiced or
paid
Accepting correct answer the risk is a response strategy where we
recognize the risk and say that it is a part of the project, normal
business practice and the team will plan to accept it accordingly.
Active listening correct answer the following is important to
understanding what others are saying both verbally and nonverbally
and for effective project management
Active listening correct answer the following is important to
understanding what others are saying both verbally and nonverbally
and for effective project management
,Activities are connected to two types of deliverables: correct answer
Project management - communications, planning, execution, etc.
Project specific to the desired end result of this project
activities correct answer are the starting point for developing the
project schedule because they identify specific work that will need to
occur in order to execute the project.
Activity Estimate Range correct answer (P−O)
Activity Estimate Standard Deviation correct answer P−O/6
Adjourning correct answer This only occurs when all the team's work
has been completed and the team is no longer required. This may occur
at any time in the project life cycle.
Administrative activities correct answer during the project closing
phase include performance report preparation, return of assets to the
sponsoring organizations, archival of records, and documentation of
lessons learned.
Advantages of Functional (Departmentalized) correct answer Lines of
authority are clear.
Departmental work is easily prioritized by identified departmental
authority.
, There is flexibility in the use of staff.
Subject matter experts (SME) available to work on multiple projects.
Knowledge and experience readily shared between functional
specialists.
Technical continuity exists within the organization.
Professional growth and career paths for the staff are clearly defined.
Advantages of Functional (Departmentalized) correct answer Lines of
authority are clear.
Departmental work is easily prioritized by identified departmental
authority.
There is flexibility in the use of staff.
Subject matter experts (SME) available to work on multiple projects.
Knowledge and experience readily shared between functional
specialists.
Technical continuity exists within the organization.
Professional growth and career paths for the staff are clearly defined.
Advantages of Matrix correct answer Central focus is the project.
Project managers have access to a large reservoir of technically skilled
people. Potentially more access to SMEs as needed. More chance to get
the most appropriate SME.
Project team members have less anxiety about the future.
Customer issues are responded to quickly.