CQM-C EXAM|COMPLETE STUDY GUIDE
WITH HIGH YIELD QUESTIONS AND 100%
RIGHT/VERIFIED ANSWERS|A
GUARANTEED PASS|ALREADY GRADED A
|LATEST UPDATED VERSION 2025.
The purpose of Construction Quality Management is to: - CORRECT
ANSWERS.✔️✔️Achieve the quality established by properly developed
requirements through the combined responsibility, but seperate efforts of
contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that
construction is performed. - CORRECT ANSWERS.✔️✔️According to plans and
specifications, on time, within a defined budget and a safe work environment.
Partnering relationships are based upon: - CORRECT ANSWERS.✔️✔️Building
trust and dedication to common goals
It is the responsibility of Quality Assurance Personnel to: - CORRECT
ANSWERS.✔️✔️Periodically verify that the contractors system of control is
working effectively.
An effective contractor quality control program will: - CORRECT
ANSWERS.✔️✔️Be an incentive for work to be done correctly the first time
resulting in earlier completion, reduced field overhead costs, and greater profits.
The success or failure of all contractors is based upon: - CORRECT
ANSWERS.✔️✔️The ability to control costs, finance work, estimate jobs, schedule
the work, and maintain effective quality control.
SUCCESS
, STUDYSAGE
Quality Assurance Personnel have the responsibility to: - CORRECT
ANSWERS.✔️✔️Require contractors to maintain the quality specified in the plans
and specifications.
Inspection is: - CORRECT ANSWERS.✔️✔️The process by which ongoing and
completed work is examined
During the punch-out inspection of a project: - CORRECT ANSWERS.✔️✔️Quality
Assurance Personnel must assure that the contractor prepares a punch-list and
makes corrections.
If there is a disagreement whether the contractors work complies with the
contract: - CORRECT ANSWERS.✔️✔️The government makes the final
determination
Characteristics that describe a definable feature of work include: - CORRECT
ANSWERS.✔️✔C ️ ross-referenced listings to the contractors construction
schedule that may have more than one definable feature under a section of the
specifications.
The _____________________ consists of daily checks of the work to assure
continuing compliance with contract requirements. - CORRECT
ANSWERS.✔️✔️Follow-up phase
The Quality Assurance Plan: - CORRECT ANSWERS.✔️✔️Is a government
management tool establishing staffing, training, pre-award activities, and
surveillance activities.
SUCCESS