TEST BANK For, Information Technology Project Management 9th Edition

Beoordeling
-
Verkocht
-
Pagina's
87
Cijfer
A+
Geüpload op
26-04-2025
Geschreven in
2024/2025

TEST BANK For, Information Technology Project Management 9th Edition TEST BANK For, Information Technology Project Management 9th Edition TEST BANK For, Information Technology Project Management 9th Edition TEST BANK For, Information Technology Project Management 9th Edition TEST BANK For, Information Technology Project Management 9th Edition TEST BANK For, Information Technology Project Management 9th Edition

Meer zien Lees minder
Instelling
TESTSBANK
Vak
TESTSBANK











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Gekoppeld boek

Geschreven voor

Instelling
TESTSBANK
Vak
TESTSBANK

Documentinformatie

Geüpload op
26 april 2025
Aantal pagina's
87
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

TO GET ALL CHAPTERS EMAIL ME AT>>>>>
TO GET THE FULL DOCUMENT EMAIL ME AT>>>>>

TEST BANK For Information Technology Project Management
9th
Edition Kathy Schwalbe,Verified
Chapters




Page 1 of 416

, TO GET THE FULL DOCUMENT EMAIL ME
AT>>>>>



True / False

1.Until the 1980s, project management primarily focused on providing
schedule and resource data to top management in the military, computer, and
construction industries.
a.True
b.False
ANSWER True
: Feedback: Until the 1980s, project management
RATIONAL primarily
on providingfocused
schedule and resource data to top
E: management in the military, computer, and
construction industries. Today’s project management
involves much more, and people in every industry and
POINTS: 1
every country manage projects.
DIFFICULTY Difficulty:
: Easy p.2
REFERENC INFO.SCHW.1
ES: 4.1 - LO: 1-1
LEARNING United States - BUSPROG:
OBJECTIVES: Technology Introduction
NATIONAL Bloom's: Knowledge
STANDARDS:
2.A difference between operations and projects is that operations end when
TOPICS:
their objectives have been reached, whereas projects do not.
KEYWORDS:
a.True
b.False
ANSWER False
: Feedback: Projects are different from operations in
RATIONAL that they
end beentheir objectives have been reached or the
has when
E:
POINTS: project
terminated. 1
DIFFICULTY Difficulty:
: Moderate p.4
REFERENC INFO.SCHW.14.2 - LO: 1-2
ES: United States - BUSPROG:
LEARNING Analytic What is a Project?
OBJECTIVES: Bloom's: Comprehension
NATIONAL
STANDARDS:
3. Every project should have a well-defined
TOPICS:
objective.
a. True
KEYWORDS: Page 2 of 416

,2



b.
False True
ANSWER: Feedback: A project has a unique purpose. Every project
RATIONAL should have a well-defined objective.
POINTS:
E: 1
DIFFICULTY Difficulty:
: Easy p.6
REFERENC
INFO.SCHW.1
ES: 4.2 - LO: 1-2
LEARNING United States - BUSPROG:
OBJECTIVES: Analytic What is a Project?
NATIONAL Bloom's: Knowledge
4. Projects should be developed in
STANDARDS:
increments.
TOPICS:
a.True
KEYWORDS:
b.False
ANSWER True
: Feedback: A project is developed using progressive
RATIONAL elaboration. Projects are often defined broadly when they
E: begin, and as time passes, the specific details of the
project become clearer. Therefore, projects should be
POINTS: developed in increments.
DIFFICULTY 1
: Difficulty:
REFERENC Moderate p.6
ES: INFO.SCHW.14.2 -
LEARNING LO: 1-2
OBJECTIVES: United States - BUSPROG:
NATIONAL Analytic What is a Project?
STANDARDS:
5. Resources in a projectBloom's:
should beComprehension
used effectively because they
TOPICS:
are limited.
KEYWORDS:
a.True
b.False
ANSWER True
: Feedback: A project requires resources, often from
RATIONAL variousResources, however, are limited and must
areas.
be used effectively to meet project and other
E: corporate goals.
POINTS:
DIFFICULTY 1
: Difficulty: Moderate
REFERENC p. 7
INFO.SCHW.14.2 - LO: 1-
ES:
NATIONAL STANDARDS: 2 United States - BUSPROG:
Analytic
LEARNING
OBJECTIVE
TOPICS: What is a Project?
Page 3 of 416
S:

, 3



KEYWORD Bloom's:
S: Comprehension




Page 3 of 416
€19,98
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten

Maak kennis met de verkoper
Seller avatar
Kehlani

Maak kennis met de verkoper

Seller avatar
Kehlani Howard Community College
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1
Lid sinds
8 maanden
Aantal volgers
0
Documenten
535
Laatst verkocht
5 maanden geleden
Nursing Education Agencies

ON THIS PAGE YOU WILL FIND VALID (WESTERN GOVERNORS UNIVERSITY) EXAMS & OTHERS eg TESTSBANKS, SOLUTION MANUALS, BSN246 HESI, BIOS , TFM08, WGU D027 AND WGU D236 PATHO etc.... We have just re-established our shop, my aim is to elevate and guide students academically with actual guides and exams 100% verified .Incase you don't find the exam that you are looking for, feel free to inbox me and request any exam. My prices are never fixed, always negotiable , WELCOME ,LETS BEGIN.

Lees meer Lees minder
0,0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Veelgestelde vragen