100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4.2 TrustPilot
logo-home
Presentatie

INF3708_ASSIGNMENT_02_2022_S2_correctSoftware Project Management

Beoordeling
-
Verkocht
-
Pagina's
5
Geüpload op
31-01-2022
Geschreven in
2021/2022

QUESTION 1 [30 Marks] QUESTION ON CHAPTER 5 1.1 Discuss the software efforts estimation techniques according to your prescribe textbook by Hughes and Cotterell (2009). In addition, fine at least one journal article that discussed software project estimation techniques/project estimation techniques and summary the techniques discussed in the article. Please remember to include the title of the article your reviewed. (20) 1.2. COCOMO is a cost estimation model that was built around equation. Provide the equation and describe the variables in Boehm’s equation for calculating effort in the use of the COCOMO model. (3) 1.3. Three systems with the following estimated lines of code were identified. Using Boehm’s equation, calculations and identify which year each system will be completed. Which system can be completed in three years? N: B show all your calculations. (7) System Line of code System type A 17862 Semi-detached mode B 10762 Semi-detached mode C 22132 Organic mode Table 1 for Question 1: System details COCOM Constants for calculation are made available in table 5.4 of your textbook, page 121.

Meer zien Lees minder
Instelling
Vak









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Studie
Vak

Documentinformatie

Geüpload op
31 januari 2022
Aantal pagina's
5
Geschreven in
2021/2022
Type
Presentatie
Persoon
Onbekend

Onderwerpen

Voorbeeld van de inhoud

Software Project Management

INF3708
Assignment 02: Due date 20 September 2019 Compulsory

ASSIGNMENT 02 - SEMESTER 2

Total Mark: 133 Marks = 100%

Mark weight: 60%

ASSIGNMENT 02
Due date 20 September 2019
Study material Hughes & Cotterell: Chapters 5 - 9
Total marks 133 marks
If your assignment is late, please DO NOT PHONE OR E-MAIL asking for an extension but include a note in
your assignment stating the reason for the late submission and we will decide whether or not it will be
marked.




Instructions:

1. Download and complete this assignment and submit online in a .pdf format by performing the calculations.

2. The following unique number has to be assigned to the assignment:

UNIQUE NUMBER:
758039

3. Show all your working (calculations).




This study source was downloaded by 100000835818796 from CourseHero.com on 01-31-2022 09:27:36 GMT -06:00


https://www.coursehero.com/file/44887039/INF3708-ASSIGNMENT-02-2019-S2-correctpdf/

, Questions on Chapter 5 - 7



QUESTION 1 [30 Marks]

QUESTION ON CHAPTER 5

1.1 Discuss the software efforts estimation techniques according to your prescribe textbook by Hughes
and Cotterell (2009). In addition, fine at least one journal article that discussed software project estimation
techniques/project estimation techniques and summary the techniques discussed in the article. Please
remember to include the title of the article your reviewed.
(20)

1.2. COCOMO is a cost estimation model that was built around equation. Provide the equation and
describe the variables in Boehm’s equation for calculating effort in the use of the COCOMO model.
(3)

1.3. Three systems with the following estimated lines of code were identified. Using Boehm’s
equation, calculations and identify which year each system will be completed. Which system can be
completed in three years? N:B show all your calculations. (7)

System Line of code System type

A 17862 Semi-detached mode
B 10762 Semi-detached mode
C 22132 Organic mode
Table 1 for Question 1: System details

COCOM Constants for calculation are made available in table 5.4 of your textbook, page
121.



QUESTION 2 [24 Marks]

QUESTIONS ON CHAPTER 6


2.1 Consider the following list of tasks with dependencies and estimated durations reflected
in table 2 and draw a CPD network diagram activity-on-node diagram to illustrate the
interaction of the activities. Include the calculations of all the values on the nodes forward
pass (earliest date) and backward pass (latest date). Note: please use the notation
example in your textbook. (14)




Activity Duration Predecessor

A 4 day -
B 2 days A
C 3 days A
D 2 days C
E
This study source was downloaded by 100000835818796 from5 days
CourseHero.com on B09:27:36 GMT -06:00
01-31-2022
F 7 days E
https://www.coursehero.com/file/44887039/INF3708-ASSIGNMENT-02-2019-S2-correctpdf/
€8,36
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten

Maak kennis met de verkoper
Seller avatar
Allanswers34
1,0
(1)

Maak kennis met de verkoper

Seller avatar
Allanswers34 University of Bristol
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
3
Lid sinds
3 jaar
Aantal volgers
3
Documenten
50
Laatst verkocht
3 jaar geleden

1,0

1 beoordelingen

5
0
4
0
3
0
2
0
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Veelgestelde vragen