Garantie de satisfaction à 100% Disponible immédiatement après paiement En ligne et en PDF Tu n'es attaché à rien 4.2 TrustPilot
logo-home
Examen

PMG201c - 141.

Note
-
Vendu
-
Pages
27
Qualité
A
Publié le
02-07-2024
Écrit en
2023/2024

Exam of 27 pages for the course studies at studies (PMG201c - 141.)

Établissement
Cours










Oups ! Impossible de charger votre document. Réessayez ou contactez le support.

École, étude et sujet

Cours

Infos sur le Document

Publié le
2 juillet 2024
Nombre de pages
27
Écrit en
2023/2024
Type
Examen
Contenu
Questions et réponses

Sujets

Aperçu du contenu

PMG201c - 141
The network diagram can be used to:
A. Help to justify project quality metrics
B. Identify project resource requirements
C. Show project schedule performance over time
D. Control the cost performance of the project
E. Help to identify riskier activities - CORRECT ANSWER-C

All of the following are responsible for documenting lessons learned, except:
A. Project manager
B. Project team
C. Key stakeholders
D. Key competitors - CORRECT ANSWER-D

Being prepared to do a complete job of developing and finalizing the scope
baseline requires that you have done a thorough and timely job of identifying and
analyzing stakeholders, and of collecting requirements. The development of the
scope baseline can best be described as involving:
A. The functional managers
B. The project team
C. All the stakeholders
D. The business analyst - CORRECT ANSWER-B

Project scope differs from product scope in that:
A. Project scope is the work that needs to be accomplished to deliver a product,
service, or result.
B. Project scope completion is measured against the features, functions, and
product requirements.
C. Product scope completion is measured against the project management plan
including all subsidiary plans.
D. Product scope is the work that needs to be accomplished to complete a
project - CORRECT ANSWER-A

Which of the following is NOT true regarding milestones?
A. Identify major events of the project deliverables

,B. There are some points in time that have no duration
C. They are supported by activities on detailed schedules
D. They are completely defined in the project charters - CORRECT ANSWER-D

The five project management process groups as described in the PMBOK®
Guide and discussed in the preceding lesson are:
A. Define, measure, analyze, improve, control
B. Kickoff, requirements, plan, schedule, control
C. Requirements, design, development, testing, implementation
D. Initiating, planning, executing, monitoring and controlling, closing - CORRECT
ANSWER-D

Which one of these is not the major source of conflict that a project manager may
influence?
A. Project Resources
B. Project team
C. Project priorities
D. Project management - CORRECT ANSWER-D

During execution, the project manager determines that a change is needed to the
material purchased for the project. The project manager calls a meeting of the
team to plan how to make the changes. This is an example of
A. Management by objectives
B. Lack of a change management plan
C. Good team relations
D. Lack of a clear work breakdown structure - CORRECT ANSWER-B

If "develop online modules" needs to finish before "review online modules" can
finish, that is called a:
A. Finish to start a relationship.
B. Start to start a relationship.
C. Start to finish relationship.
D. Finish-to-finish relationship. - CORRECT ANSWER-D

You are assigned as the project manager in the middle of the project. The project
is within the baselines, but the customer is not happy with the performance of the
project. What is the first thing you should do?

, A. Discuss it with the project team
B. Recalculate baselines
C. Renegotiate the contract
D. Meet with the customer - CORRECT ANSWER-D

True or False: Project quality focuses on the goods and services.
A. False
B. True - CORRECT ANSWER-A

A significant event in a project that may indicate completion of a major phase is
a/an:
A. Activity
B. Milestone
C. Work package
D. Deliverable - CORRECT ANSWER-B

Which of the following is included in a project charter?
A. The business case for the project
B. A risk management strategy
C. Detailed resource estimates
D. Work package estimates - CORRECT ANSWER-A

We discussed three types of matrix organizations, they are:
A. Light, Medium and Heavy
B. Weak, Medium Strength, and Strong
C. Weak, Balanced and Strong
D. Light, Mid-strength, and Strong - CORRECT ANSWER-C

All of the following tools and techniques can be valuable in risk identification,
EXCEPT:
A. Reviewing and evaluating project documents
B. SWOT (Strengths, Opportunities, Weaknesses. Threats)
C. EVM (Earned Value Management)
D. Reviewing similar projects executed in the past - CORRECT ANSWER-C

When you have good historical information that can be used in a reliable formula
or model, you will probably use:
7,00 €
Accéder à l'intégralité du document:

Garantie de satisfaction à 100%
Disponible immédiatement après paiement
En ligne et en PDF
Tu n'es attaché à rien

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
GOLDSOLUTIONS Chamberlain College Of Nursing
S'abonner Vous devez être connecté afin de pouvoir suivre les étudiants ou les formations
Vendu
4987
Membre depuis
2 année
Nombre de followers
60
Documents
17118
Dernière vente
2 jours de cela

4,2

69 revues

5
45
4
8
3
8
2
3
1
5

Récemment consulté par vous

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions