Emphasizing areas of agreement and deemphasizing areas of non-agreement represents which
type of conflict resolution mode?
a. Confrontation
b. Compromise
c. Forcing
d. Smoothing - Answers D
Activates with zero-time duration are called:
a. Low-slack activities
b. No-slack activities
c. Milestone activities
d. Special activities - Answers C
Which of the following is false concerning the critical path in a network?
a. It is the longest path in the network
b. It is the shortest amount of time in which the project can be completed
c. It is that contains the greatest number of activities
d. It is the path where each activity has zero slack - Answers C
Which of the following schedule compression techniques usually requires adding more
resources to each work package that is being compressed?
a. Overtime
b. Crashing
c. Outsourcing
d. Descoping - Answers B
Of the following, which is the logical order of the project management processes?
a. Initiating, planning, monitoring and controlling, executing, closing
b. Initiating, planning, executing, monitoring and controlling, closing
, c. Planning, initiating, monitoring and controlling, executing, closing
d. Planning, initiating, executing, closing, monitoring and controlling - Answers B
All of the following are true statements about the project life cycle, except for which one?
a. The project life cycle defines the work to be done in each phase of the project
b. The project life cycle defines the deliverables that each phase will create
c. The project life cycle defines who involved in each phase
d. The project life cycle defines how much each phase will cost - Answers D
What is the only tool and technique used during scope verification?
a. Inspection
b. Quality control
c. Stakeholder analysis
d. Defect repair review - Answers A
Which one of the following is NOT one of the quality management processes?
a. Quality control
b. Quality adherences
c. Quality control
d. Quality assurance - Answers B
Mike, a project manager in your company, is falling behind on the project schedule. He has
elected to crash the project. What is crashing?
a. Adding lag time between all project activities
b. Adding lead time between all project activities
c. Adding additional project resources to the project work
d. Removing all unneeded project deliverables - Answers C
Which estimating technique uses a similar project to predict how long the current project will
take to complete?
a. Analogous estimating