QUESTIONS AND
CORRECT ANSWERS
GRADED A+ 2025-2026
Once the make-or-buy analysis is completed, which document defines the project
delivery method? - ANS-Procurement strategy
A project is just beginning, and management creates a long list of potential
stakeholders. Which statement about identifying and engaging stakeholder, is correct?
- ANS-stakeholder satisfaction should be identified immediately and managed as a
project objective.
Which is an example of leveraging evolving trends and emerging practices in project
integration management? - ANS-hybrid methodologies
What should a project manager use to determine how much money is needed to
complete a project? - ANS-earned value analysis (EVA)
The project manager is creating the communications management plan. Which group
of inputs is required to begin? - ANS-project charter, project management plan, and
project documents
A project is in progress and about to move to a different phase, according to the plan.
This will be a good opportunity for the project manager to: - ANS-review and update
stakeholder engagement
, A new project has been set. Four main stakeholders besides the project manager and
four other team members have been identified.How many communication channels are
available? - ANS-C-35 n*(n-1)/2= 9*8/2=72/2=36
A project manager is preparing to meet with three crucial project stakeholders on a
new project. Which tools and techniques can the project manager use to capture
stakeholder interest? - ANS-data analysis and communication skills
Select three processes that are associated with Project Schedule Management? (Choose
three.) - ANS-define activities, estimate activity durations, develop schedule
What are the project management processes associated with project quality
management? - ANS-plan quality management, manage quality, and control quality
In an adaptive project environment, which action helps the project manager ensure
that the team is comfortable with charges? - ANS-giving access to information to the
team and frequent team checkpoints
The activity of tailoring is necessary because: - ANS-each project is unique, and the
members of the project team should select the appropriate tools, techniques, inputs,
and outputs from the PMBOK Guide.
When developing the project schedule, a project manager uses decomposition and
rolling wave planning techniques in this process: - ANS-define activities
Which of the following tasks focuses on decomposing work packages? - ANS-define
activities
During what project management process does the project manager invest the most
effort into creating the work breakdown structure (WBS)? - ANS-Planning
Given the following information:✑ Activity A takes one week.✑ Activity B takes three
weeks.✑ Activity C takes two weeks.✑ Activity D takes five weeks.✑ Activity A starts
at the same time as Activity B.✑ Activity C follows Activity B and Activity A.✑ Activity
D follows Activity C.