The project manager and team should consider each process along with its inputs,
tools and outputs. As a result, they should choose which are applicable. This effort is
known as - ANS-Tailoring
In Initiating, a project charter is created. According to the PMBOK, which person or
group may help write the charter? - ANS-Project management team
The Monitoring and Controlling Process Group involves: - ANS-Tracking, reviewing, and
orchestrating the progress of the project
Much information is collected and distributed during the life of the project. Data that
is collected form controlling processes and analyzed in context is called: - ANS-Work
performance information
The project manager should perform the Initiating processes at the start of each phase
in order to: - ANS-Keep the project focused on the business need
, As Planning occurs, more and more is known about the project and the project
management plan becomes increasingly detailed. This detailing is known specifically
as: - ANS-Progressive elaboration
The process group that involves coordinating people and resources, managing
stakeholder expectations and completing the work defined in the project management
plan is known as: - ANS-Executing
The Process group that contains more than 50% of the processes is known as: - ANS-
Planning
>Direct and Manage Project Work is the process of leading and performing the work
defined in the project management plan. There are several outputs from this process.
The only one defined as typically tangible components completed to meet the project
objectives is: - ANS-Deliverables
In conjunction with the project manager, which person or group needs to address
every process and the project environment to determine the level of implementation
for each process? - ANS-Project team
The key benefit of one of the Integration processes is that it allows stakeholders to
understand the current state of the project, the steps taken, budget, schedule, and
scope forecasts. This process is known as: - ANS-Monitor and Control Project Work
The project manager should participate in the development of the project charter to
better understand the project requirements. Understanding these requirements will
better allow for: - ANS-Efficient resource allocation to project activities
As a change control expert, you are asked to work on a plan that documents how
changes will be controlled and monitored on the project. Additionally you are told it
will ultimately become part of the project management plan. This document is known
as a: - ANS-Change management plan
Direct and Manage Project Work requires review of all project changes and the
implementation of approved changes. This may lead to corrective action which is
defined as: - ANS-An intentional activity that realigns the performance of the project
work with the project management plan