ACI Concrete Field Testing Technician – Grade 1 Certification Exam for the 2026/2027 cycle, featuring complete exam style questions with accurate, up-to-date answers.

Puntuación
-
Vendido
1
Páginas
41
Grado
A+
Subido en
15-12-2025
Escrito en
2025/2026

ACI Concrete Field Testing Technician – Grade 1 Certification Exam for the 2026/2027 cycle, featuring complete exam style questions with accurate, up-to-date answers.

Institución
ACI Concrete Field Testing Technician – Grade 1 C
Grado
ACI Concrete Field Testing Technician – Grade 1 C











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
ACI Concrete Field Testing Technician – Grade 1 C
Grado
ACI Concrete Field Testing Technician – Grade 1 C

Información del documento

Subido en
15 de diciembre de 2025
Número de páginas
41
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

ACI Concrete Field Testing Technician – Grade 1
Certification Exam for the 2026/2027 cycle,
featuring complete exam-style questions with
accurate, up-to-date answers.

Q1. Start molding specimens for strength tests within 30
minutes after fabricating the composite sample.

A. True
B. False
B. False

ASTM C172 -Para (4.1.2) - Start molding.
specimens for strength tests within 15 min after fabricating the
composite sample.
Q2. The maximum allowable time between obtaining the first
and last portions of the composite sample may not exceed 5
minutes.

A. True
B. False
B. False

ASTM C172 - Para (4.1)- The elapsed time shall not exceed 15
min. between obtaining the first and final portions of the
composite sample.
Q3. The composite concrete sample must be protected from
sun, wind, contamination and rapid evaporation.

A. True
B. False

,A. True

ASTM C172 - Para (4.1.2)
Q4. If the concrete contains aggregates larger than those that
are appropriate for a size of mold or equipment used, the
sample should be wet sieved before making the test.

A. True
B. False
A. True

ASTM C172- Para (6.1)
Q5. The composite sample should not be remixed before
beginning any tests.

A. True
B. False
B. False

ASTM C172-Para (4.1.1) -The sample shall be combined and
remixed with a shovel the minimum amount necessary to ensure
uniformity and compliance with the maximum time limits
Q6. Sampling should normally be performed, as the concrete
is discharged from the mixer.

A. True
B. False
B. False

ASTM C172-Para (5). NOTE 2—Sampling should normally be
performed as the concrete is delivered from the mixer.

To the conveying vehicle used to transport the
concrete to the forms; however, specifications may require other
points of sampling, such as the discharge of a concrete pump.

,Q7. ASTM Method C172 includes sampling from stationary
mixers, paving mixers, truck mixers, agitators, and non-
agitating equipment.

A. True
B. False
A. True

ASTM C172- Para (1.1)
Q8. After sampling is completed, start the tests for slump
and air content within:

A. 2 ½ minutes
B. 10 minutes
C. 15 minutes
D. None of the above
D. None of the above

ASTM C172- Para (4.1.2) Start tests for slump, temperature, and
air content within 5 min after obtaining the final portion of the
composite sample.
Q9. In any case, do not obtain samples until:

A. All the water and admixtures have been added to the
concrete
B. 200 revolutions of the drum have been obtained
C. ½ of the water has been added
D. None of the above
A. All the water and admixtures have been added to the concrete.

ASTM C172- Para (5.2.3). In any case do not obtain samples until
after all of the water has been added to the mixer.
Q10. No samples shall be taken before_________ or
after_________ of the batch has been discharged.

, A. 10% or after 90%
B. 20% or after 90%
C. 20% or after 80%
D. None of the above
A. 10% or after 90%

ASTM C172- Para (5.2.1).

NOTE 3—No samples should be taken before 10 % or after 90 %
of the batch has been discharged.

Due to the difficulty of determining the actual quantity of concrete
discharged, the intent is to provide samples that are
representative of widely separated portions, but not the beginning
and the end of the load.
Q11. When strength tests are to be made, the minimum size
of the composite sample shall be:

A. ¼ cubic foot
B. 1 cubic foot
C. Any convenient size
D. 1 Wheelbarrow
B. 1 cubic foot

ASTM C172- Para (5.1).

Make the samples to be used for strength tests a minimum of 28
L (1 ft3).
Q12. Sample the concrete from the chute of a truck mixer by:

A. Raising chute to stop the flow and scoop concrete from
there into the slump cone and cylinder molds
B. Passing a receptacle completely through the discharge
steam or by completely diverting the discharge into the
sample container
$25.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
wise254 Chamberlain College Of Nursng
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
52
Miembro desde
1 año
Número de seguidores
3
Documentos
2362
Última venta
5 horas hace
StudySphere

Success starts with the right resources, and these study documents are exactly what you need to stay ahead. Carefully crafted, easy to understand, and packed with key points, these notes take the stress out of studying. Whether you're aiming for top grades or just need a clearer way to review, these materials are made to help you succeed. Stop struggling with scattered information—get organized, get focused, and get results. Download now and experience the difference smart studying makes!

Lee mas Leer menos
5.0

570 reseñas

5
558
4
4
3
5
2
2
1
1

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes