Purpose Statement: DBIA is the only organization that _____ , _____, and _____ best
practices in design-build project delivery.
Give this one a try later!
- defines
- teaches
- promotes
The 2 main responsibilities of the owner under ALL delivery systems: Executing ______;
and Executing actual _____ _____.
Give this one a try later!
, - procurement
- project delivery
In DBB, the Owner has a "_____ relationship" with the Contractor.
Give this one a try later!
Spearing Relationship
_____ _____ are high level principles.
Give this one a try later!
Best practices
_____ ______ was not a contractor, architect, or engineer; but the embodiment of all 3.
Give this one a try later!
Master-Builder
What creates innovation potential in DB?
Give this one a try later!
, Collaboration between the Owner, Contractor, and Designer
IMPLEMENTING TECHNIQUE No. 1(G): Owners should understand all _____ constraints
imposed or _____ afforded by their legislative, regulatory, or internal requirements.
Give this one a try later!
- procurement
- flexibilities
Performance Requirements have challenges in developing objective and _____ _____ to
validate performance.
Give this one a try later!
definable standards
VISION: DBIA will be the industry's _____ resource for leadership, education, objective
expertise and best practices for the successful integrated delivery of _____ projects.
Give this one a try later!
- preeminent
- capital
What 2 main things do EPC contract terms include?
, Give this one a try later!
- liquidated damages
- limitations of liability
Delivery systems alone, do not predict _____
Give this one a try later!
success
Best Value Weighted Criteria: _____ Score is determined from multiple criteria and
weighted scoring.
Give this one a try later!
Technical
What contract approach does IPD tend to use?
Give this one a try later!
Target Price
Owners should make strategic decisions to take full advantage of _____ _____.
practices in design-build project delivery.
Give this one a try later!
- defines
- teaches
- promotes
The 2 main responsibilities of the owner under ALL delivery systems: Executing ______;
and Executing actual _____ _____.
Give this one a try later!
, - procurement
- project delivery
In DBB, the Owner has a "_____ relationship" with the Contractor.
Give this one a try later!
Spearing Relationship
_____ _____ are high level principles.
Give this one a try later!
Best practices
_____ ______ was not a contractor, architect, or engineer; but the embodiment of all 3.
Give this one a try later!
Master-Builder
What creates innovation potential in DB?
Give this one a try later!
, Collaboration between the Owner, Contractor, and Designer
IMPLEMENTING TECHNIQUE No. 1(G): Owners should understand all _____ constraints
imposed or _____ afforded by their legislative, regulatory, or internal requirements.
Give this one a try later!
- procurement
- flexibilities
Performance Requirements have challenges in developing objective and _____ _____ to
validate performance.
Give this one a try later!
definable standards
VISION: DBIA will be the industry's _____ resource for leadership, education, objective
expertise and best practices for the successful integrated delivery of _____ projects.
Give this one a try later!
- preeminent
- capital
What 2 main things do EPC contract terms include?
, Give this one a try later!
- liquidated damages
- limitations of liability
Delivery systems alone, do not predict _____
Give this one a try later!
success
Best Value Weighted Criteria: _____ Score is determined from multiple criteria and
weighted scoring.
Give this one a try later!
Technical
What contract approach does IPD tend to use?
Give this one a try later!
Target Price
Owners should make strategic decisions to take full advantage of _____ _____.