CH1 - Which of the following is NOT a popular time management tool or technique? Select one: a. Gantt charts b. Project constraint diagrams c. Project network diagrams d. Critical path analysis [ Ans: ] The correct answer is: Project constraint diagrams CH1 - Project __________ management is an overarching function that affects and is affected by all of the other knowledge areas. Select one: a. human resource b. integration c. scope d. quality [ Ans: ] The correct answer is: integration 2 CH1 - A __________ is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format. Select one: a. critical path b. network diagram c. Gantt chart d. resource histogram [ Ans: ] The correct answer is: Gantt chart CH1 - Work done in organizations to sustain the business is the definition of: Select one: a. programs b. operations c. projects d. productivity [ Ans: ] The correct answer is: operations CH1 - A group of related projects is a(n): Select one: 3 a. portfolio b. program c. application d. operation [ Ans: ] The correct answer is: program CH1 - Which of the following is NOT a component of project management's triple constraint? Select one: a. time b. quality c. cost

Mostrar más Leer menos
Institución
ISDS 351
Grado
ISDS 351










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
ISDS 351
Grado
ISDS 351

Información del documento

Subido en
11 de diciembre de 2025
Número de páginas
27
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

1

ISDS 351 Final Questions and Answers (100%
Correct Answers) Already Graded A+
CH1 - Which of the following is NOT a popular time-
management tool or technique?

Select one:

a. Gantt charts

b. Project constraint diagrams

c. Project network diagrams

d. Critical path analysis [ Ans: ] The correct answer is:
Project constraint diagrams

CH1 - Project __________ management is an overarching
function that affects and is affected by all of the other
knowledge areas.

Select one:

a. human resource

b. integration

c. scope

d. quality [ Ans: ] The correct answer is: integration

,2
CH1 - A __________ is a standard format for displaying
project schedule information by listing project activities
and their corresponding start and finish dates in a
calendar format.

Select one:

a. critical path

b. network diagram

c. Gantt chart

d. resource histogram [ Ans: ] The correct answer is: Gantt
chart

CH1 - Work done in organizations to sustain the business
is the definition of:

Select one:

a. programs

b. operations

c. projects

d. productivity [ Ans: ] The correct answer is: operations

CH1 - A group of related projects is a(n):

Select one:

, 3
a. portfolio

b. program

c. application

d. operation [ Ans: ] The correct answer is: program

CH1 -

Which of the following is NOT a component of project
management's triple constraint?

Select one:

a. time

b. quality

c. cost

d. scope [ Ans: ] The correct answer is: quality

CH1 - __________ are the people involved in or affected by
project activities and include the project sponsor, project
team, support staff, customers, users, suppliers, and even
project opponents.

Select one:

a. Human resource personnel
$13.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Guru01 Chamberlain College Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
215
Miembro desde
1 año
Número de seguidores
32
Documentos
20686
Última venta
1 día hace

3.8

36 reseñas

5
15
4
8
3
7
2
1
1
5

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes