The contracting process consists of three Contract Life Cycle Phases? - Correct
Answers -Pre-award, Award, and Post-award
The pre-award phase consists of two primary activities? - Correct Answers -Develop
Solicitation, Develop Offer
In planning the solicitation, the buying activity must assess the need and analyze the
requirement as well as make sure that contract outcomes will be measurable and
properly incentivized. The buying activity must also verify the availability of funds? -
Correct Answers -FAR part 7, Acquisition Planning, and FAR part 11, Describing
Agency Needs, are key resources
Buying activities must also conduct market research to identify potential suppliers,
evaluate if the requirement is achievable, and perform any pre-offer conferences or
communication. - Correct Answers -FAR part 10, Market Research, is a key resource
and is required by law
Market Research is a continuous process throughout all phases of? - Correct Answers -
the contract life cycle
Before finalizing the solicitation, the contracts manager will participate in choosing a
contract type and contracting method, help determine applicable regulations, and assist
in building an evaluation strategy for offers? - Correct Answers -FAR part 16 is the
primary source for information about contract types.
To issue the solicitation, the buying activity must determine the need and means of
publicizing the solicitation so that offerors are aware of the potential business
opportunity? - Correct Answers -FAR part 5 addresses publicizing contract actions.
In response to a solicitation, the seller will submit an offer? - Correct Answers -The offer
must align with the offeror's overall sales plan and be within the offeror's overall risk
strategy
Acquisition Team Members - Correct Answers -Acquisition Team as consisting of all
participants in Government acquisition including not only representatives of the
ROLES 1.1
The contracting process consists of three Contract Life Cycle Phases? - Correct
Answers -Pre-award, Award, and Post-award
The pre-award phase consists of two primary activities? - Correct Answers -Develop
Solicitation, Develop Offer
In planning the solicitation, the buying activity must assess the need and analyze the
requirement as well as make sure that contract outcomes will be measurable and
properly incentivized. The buying activity must also verify the availability of funds? -
Correct Answers -FAR part 7, Acquisition Planning, and FAR part 11, Describing
Agency Needs, are key resources
Buying activities must also conduct market research to identify potential suppliers,
evaluate if the requirement is achievable, and perform any pre-offer conferences or
communication. - Correct Answers -FAR part 10, Market Research, is a key resource
and is required by law
Market Research is a continuous process throughout all phases of? - Correct Answers -
the contract life cycle
Before finalizing the solicitation, the contracts manager will participate in choosing a
contract type and contracting method, help determine applicable regulations, and assist
in building an evaluation strategy for offers? - Correct Answers -FAR part 16 is the
primary source for information about contract types.
To issue the solicitation, the buying activity must determine the need and means of
publicizing the solicitation so that offerors are aware of the potential business
opportunity? - Correct Answers -FAR part 5 addresses publicizing contract actions.
In response to a solicitation, the seller will submit an offer? - Correct Answers -The offer
must align with the offeror's overall sales plan and be within the offeror's overall risk
strategy
Acquisition Team Members - Correct Answers -Acquisition Team as consisting of all
participants in Government acquisition including not only representatives of the