100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

PJM Practice questions with Correct Answers 100% Pass

Puntuación
-
Vendido
-
Páginas
31
Grado
A+
Subido en
07-12-2025
Escrito en
2025/2026

PJM Practice questions with Correct Answers 100% Pass

Institución
Pjm
Grado
Pjm











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Pjm
Grado
Pjm

Información del documento

Subido en
7 de diciembre de 2025
Número de páginas
31
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

PJM Practice questions with

Correct Answers 100% Pass


A Heavy Load Voltage Schedule Warning is typically issued ___ prior to actual

implementation. - CORRECT ANSWER-c. 4 hours

The following would be considered non-critical plant load (Select 2) - CORRECT

ANSWER-A. Office Area Air Conditioners

C. Lighting

During a Cold Weather Alert, PJM will take which of the actions - CORRECT

ANSWER-D. Assume an unavailability rate for schedule generation

When PJM issues a High System Voltage Message, the GO should have its units

operate at: - CORRECT ANSWER-B. The lower end of their voltage bandwidth

What would the reportable Emergency Reducible Generation be if the Generator

Output is 400 MW, Economic Min is 225 MW and the Emergency Min is 175 MW

- CORRECT ANSWER-C. 50 MW

PJM can issue the Deploy All Resources Action for - CORRECT ANSWER-D.

The entire RTO, specific Control Zones, or a subset of a Control Zone if

transmission limitations exist

,PJM has issued a Minimum Generation Alert. Your current generation is 200 MW.

The Economic Minimum is 150 MW and the Emergency Min is 125 MW. How

much ERG should be reported for this unit? - CORRECT ANSWER-B. 25MW

Which of the following steps would PJM take as part of initiating Conservative

Operations? (Select 2) - CORRECT ANSWER-A. Perform job studies looking at

the loss of multiple pieces of equipment as a single event




C. Initiate additional off-cost operation to limit or reduce flows across critical

interfaces

The purpose of the Deploy All Resources Action is to instruct all generating

resources to be on line and at full output ____ - CORRECT ANSWER-D.

Immediately upon receipt of dispatch instructions

Under the National Terrorism Advisory System (NTAS) there are two types of

alerts: Elevated Threat Alert and - CORRECT ANSWER-A. Imminent Threat

Alert

What is the requested response time for members to reply to a request for SSR

data? - CORRECT ANSWER-A. 10 minutes

You are a Generation Owner with the following units. PJM has just requested a

Supplementary Status Report (SSR). what do you report as your total "On Cost"

Steam Capacity



COPYRIGHT ALL RIGHTS RESERVED ©️ 2025

,U1: ECO max, 145 - EMR max 145 Current output 140

U2 ECO max, 550 - EMR max 145 Current output 400

U3 ECO max, 400, EMR max 410 Current output - CORRECT ANSWER-

1095MW

Why does PJM require an additional notification time of Unit testing 30 minutes

prior to the GO/MOC performing the reactive capability testing? - CORRECT

ANSWER-C. To allow PJM and TOs to make adjustments to system voltages

prior to test

When an outage requires verbal notification to PJM which PJM personnel should

be contacted? - CORRECT ANSWER-B. Master Coordinator

One of the leading causes of the 1999 Low Voltage event in PJM was ___ -

CORRECT ANSWER-B. PJM's EMS at that time had only nameplate D-curve

data for

With whom does PJM share the results of generation reactive capability tests? -

CORRECT ANSWER-A. The affected TO

With the exception of intermittent resources, Over-excited (Lagging) test results

are the values of MVAR output that can be sustained for how long? - CORRECT

ANSWER-D. 60 min

, During the PJM Peak Period Maintenance Season whit is the max amount of

consecutive days the outage can last? - CORRECT ANSWER-C. 9

When PJM requests a Reactive Reserve Check (RRC), how does the GO/MOC

report limitations or restrictions on their unit which would prevent it from being

able to follow it's reactive capability curve as recorded in eDART - CORRECT

ANSWER-A. By notifying the effect TO

What is the min time needed to submit a reactive capability test ticket via eDARt

prior to performing the test? - CORRECT ANSWER-C. 3 business days

A unit (or intermittent facility) will be considered as having passed their capability

test and require no further action if their test results are within ___ of the stated

limits - CORRECT ANSWER-D. 5%

Even if no changes are made, MOCs/GOs must review and confirm their unit

reactive capability via eDARt how ofter? - CORRECT ANSWER-D. Twice per

year

What is the penalty for units that do not meet their stated reactive capability during

reactive capability - CORRECT ANSWER-B. There is no penalty

When submitted expected capability for "new" units, what reactive capability

should be used? - CORRECT ANSWER-B. Vendor supplied D-curves




COPYRIGHT ALL RIGHTS RESERVED ©️ 2025
$13.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
KatelynWhitman West Virginia University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1106
Miembro desde
2 año
Número de seguidores
482
Documentos
34109
Última venta
2 días hace
Golden Quill Emporium Store

Get Yourself Well-Researched Study Materials to Ace Your Online& Actual Exam Tests with Confidence. STUDY LIKE A PRO WITH A WELL FORMATTED Q&A MATERIALS.

3.6

241 reseñas

5
96
4
39
3
54
2
20
1
32

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes