What stage:
Gather available data
Planning Prior to occupying TTC zone
Consider the needs of all users
Coordinate between adjacent or overlapping projects
What stage:
Design Select best traffic control alternative
based on: safety, mobility, cost, constructability
Traffic Factors, What Factors effect the design of a TTC plan
characteristics, and speed.
Traffic controls, urban
features, and traffic
generators
Long-term stationary What are the MUTCD categories of Work Duration?
Intermediate-term
stationary
short-term stationary
short-duration
mobile
Project" Module 7 Exam Questions with Correct
Answers
Save
Terms in this set (15)
What stage:
Gather available data
Planning Prior to occupying TTC zone
Consider the needs of all users
Coordinate between adjacent or overlapping projects
What stage:
Design Select best traffic control alternative
based on: safety, mobility, cost, constructability
Traffic Factors, What Factors effect the design of a TTC plan
characteristics, and speed.
Traffic controls, urban
features, and traffic
generators
Long-term stationary What are the MUTCD categories of Work Duration?
Intermediate-term
stationary
short-term stationary
short-duration
mobile