Page 1 of 63



EBOLC Project Management EXAM ALL QUESTIONS
AND CORRECT ANSWERS LATEST UPDATE THIS
YEAR


QUESTION: A project manager wants to decrease costs on a project that a consultant is

completing for her company. What costs should the project manager consider to accomplish

this?


1) Variable and fixed


2) variable and direct


3) Fixed and indirect


4) Direct and indirect - ANSWER-2) Variable and direct




QUESTION: You are having difficulty estimating the cost of a project. Which of the following

BEST describes the most probable cause of your difficulty?


1) Inadequate scope definition


2) Unavailability of desired resources


3) Lack of historical records from previous projects



1

, Page 2 of 63


4) Lack of company processes - ANSWER-1) Inadequate scope definition




QUESTION: The high-level project schedule constraints have just been determined. What

project management process group are you in?


1) Initating


2) Planning


3) Executing


4) Monitoring and Controlling - ANSWER-1) Initiating




QUESTION: Who are the following are ALWAYS stakeholders?


1) A person who does not want the project to be completed


2) An assembly line worker that will use the product of the project


3) A functional manager from the engineering department


4) A person who might lose their position in the company because of the project - ANSWER-2)

An assembly line worker that will use the product of the project




2

, Page 3 of 63


If a person or entity thinks they are a stakeholders, then they are a stakeholder, even if you

dont agree on it.




QUESTION: Which process group authorizes the project?


1) Initiating


2) Planning


3) Executing


4) Monitoring and controlling - ANSWER-1) Initiating




QUESTION: Your manager gives you a preliminary project scope statement and asks you to

begin working immediately and to provide her with a schedule. What should you do FIRST?


1) Begin estimating the activities necessary to complete the scope of work


2) Obtain a project charter and begin creating a project scope statement


3) Create an activity list and then begin to assign the activities to resources


4) Identify a team and obtain approval from their participation from their functional managers -

ANSWER-Obtain a project charter and begin creating a project scope statement




3

, Page 4 of 63


QUESTION: All of the following are parts of the project initiating processes EXCEPT?


1) Develop a product acceptance criteria


2) Determine project boundaries


3) Develop project objectives


4) Develop performance measurement baselines - ANSWER-4) Develop performance

measurement baselines




QUESTION: Who issues the project charter?


1) Sponsor


2) Project Manager


3) Project team


4) Stakeholders - ANSWER-1) Sponsor




Q; A construction project has a work package that could result in fatalities or long term

disabilities with losses of over US $2 million. The company has had a clean record in the past

and has won several safety awards. An appropriate risk response strategy is to:


1) Post a sign that describes the number of injuries to date and remind everyone to be careful



4

Información del documento

Subido en
5 de diciembre de 2025
Número de páginas
63
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$23.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
STUVIAGRADES
4.8
(1110)
Vendido
6597
Seguidores
466
Artículos
8732
Última venta
7 horas hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes