What should the project team avoid?
Give this one a try later!
Scope creep
, What two things should be measured for resources for each specific activity?
Give this one a try later!
It is necessary to estimate the types and quantities of resources required to
perform each specific activity.
For a contractor, what are two potential consequences of having a project terminated
early b a customer who is not satisfied?
Give this one a try later!
1) May incur a financial loss because of the early termination
2) May have to lay off some of the employees who were working on the
project
What is the to-complete performance index equation
Give this one a try later!
TCPI = (TBC -CEV)/ (TBC-CAC)
What three schedule elements will be affected by the actual finish times of completed
activities?
Give this one a try later!
Give this one a try later!
Scope creep
, What two things should be measured for resources for each specific activity?
Give this one a try later!
It is necessary to estimate the types and quantities of resources required to
perform each specific activity.
For a contractor, what are two potential consequences of having a project terminated
early b a customer who is not satisfied?
Give this one a try later!
1) May incur a financial loss because of the early termination
2) May have to lay off some of the employees who were working on the
project
What is the to-complete performance index equation
Give this one a try later!
TCPI = (TBC -CEV)/ (TBC-CAC)
What three schedule elements will be affected by the actual finish times of completed
activities?
Give this one a try later!