Questions
A) An established objective
B) A clear beginning and end
C) Specific time, cost and performance requirements
E) Something never been done before - correct answers What are characteristic of a project?
Writing a policy manual - correct answers When considering the following activities, which is the best
example of a project?
Defining - correct answers In the _____________ stage of the project life cycle, project objectives are
established, teams are formed, and major responsibilities are assigned.
Executing - correct answers In the _____________ stage of the project life cycle, a major portion of the
physical project work performed.
A) Managing a temporary activity
This one B) Overseeing existing operations
C) Managing a non-repetitive activity
D) Responsible for time, cost and performance trade-offs
E) Work with a group of outsiders, including vendors and suppliers - correct answersWhich of the
following is NOT typical of a project manager?
1. Defining
2. Planning
3. Executing
4. Closing - correct answersWhat are the correct order of stages within the project life cycle?
, Developing a new residential area that includes six custom homes - correct answersExample of a
program
This one A) A method to ensure projects that are important to senior management are being
implemented
B) An assessment of the risk their portfolio of projects represents
C) An overview of all project management activities
D) A metric to measure the improvement of managing projects relative to others in the industry
E) A big picture of how organizational resources are being used. - correct answersGovernance of all
project management processes and procedures helps provide senior management with all of the
following except
A) It is not limited to the private sector
B) Many opportunities are available for individuals interested in this career path
C) It improves one's ability to plan, implement and manage activities to accomplish specific
organizational objectives
This one D) It focuses primarily on technical processes
E) It is a set of tool - correct answersThe following is NOT true about project management
Outsourcing significant segments of project work - correct answersCorporate downsizing has increased
the trend toward
A) WBS
B) Budgets
This one C) Problem solving
D) Schedules
E) Status reports - correct answersWhich of these is NOT part of the "technical dimension" of project
management?
A) Work with others to create a schedule and budget
B) Need to understand project priorities so they can make independent decisions