What is NOT one of the three main issues the superintendent must be
concerned with when trying to manage construction operations.
Ans: Office communication structure
When scheduling subcontractors for the job, you should try to follow
three fundamental rules. Which of the following is NOT one of them?
Ans: Try to fit as many subcontractors into the same space at
the same time to cut back on duration.
What does it mean to order something on will-call?
Ans: Confirming an order day-of delivery that has been placed
prior.
Which is NOT a factor that negatively impacts construction
productivity?
Ans: On site meetings with the owner
What is an environmental issue that would interfere with the project
schedule and cause unexpected delays on the job?
All rights reserved © 2025/ 2026 |
, Page |2
Ans: Discovering historical or cultural artifacts while
excavating
What is a laydown area?
Ans: A designated storage area on site used for sorting out
large orders
On what kind of plan would a portable toilet, dumpsters, and on-site
parking areas be shown?
Ans: A site logistics plan
Why is it important for the job superintendent and the other members
of the onsite team to keep project diaries?
Ans: The diaries help to keep straight all of the
communications, conversations, and activities.
Why is it important to accurately report hours and cost codes on time
cards?
Ans: They provide fundamental information needed to tr ack
and monitor productivity and labor expenditures.