QUESTIONS AND CORRECT ANSWERS
Project Closeout Matching
Red Zone Meeting:
Preliminary Inspection:
Pre-Final:
System Commissioning/testing/training:
Final Inspection:
Post Occupancy Inspection: - CORRECT ANSWERS✅✅Red Zone Meeting: Optional, est
milestones
Preliminary Inspection: Optional, gov only
Pre-Final: Creates punchlist
System Commissioning/testing/training: Continuous
Final Inspection: Accept facility from contractor
Post Occupancy Inspection: Confirms warranty performance
Scheduling:
3 steps in creating a schedule - CORRECT ANSWERS✅✅1. ID activities
2. Estimate activity durations
3. Determine the sequence
Scheduling:
FF vs. TF - CORRECT ANSWERS✅✅FF - time an activity can be delayed w/o delaying
ES of successor
TF - time an activity can be delayed w/o delaying project
, Scheduling:
3 common schedule analysis techniques - CORRECT ANSWERS✅✅- Precedence
diagramming method
- Critical path method
- PERT & EVM
Construction Mgmt:
Who's role is quality control vs quality assurance? - CORRECT ANSWERS✅✅QC -
Contractor
QA - CO/PM/Inspector
Design Process, Reviews, Guidance:
Steps in design process - CORRECT ANSWERS✅✅Planning
Programming
Design
Construction
Operations
Design Process, Reviews, Guidance:
What are the products developed from each design process? - CORRECT
ANSWERS✅✅Requirements Analysis - prgm req's
Conceptual Design - bubble diagrams
Schematic Design - schematic floor plans
Design Development - scaled floor plan