GRADE A| 100% CORRECT (VERIFIED ANSWERS)
Your colleagues are discussing WBS objects and ask you to explain the functions of WBS objects. Which
of the following functions will you include in your explanation? ( 4 correct )
A. Planning costs and revenues
B. Planning dates
C. Budget management
D. Scheduling operations
E. Periodic processing
F. Confirming operations - correct answer -A. Planning costs and revenues
B. Planning dates
C. Budget management
E. Periodic processing
The operative indicator, Account Assignment Element is used when you want to plan costs for WBS
elements. True or false - correct answer -False
You are asked to explain operative indicators in SAP ERP Program and Project Management. You explain
operative indicators as defining the characteristics of WBS elements. Which of the following will you
include as examples of operative indicators? (3 correct)
A. Account assignment
B. Budgeting
C. Billing
D. Statistical
E. Planning - correct answer -A. Account assignment
C. Billing
E. Planning
,When activities are assigned to WBS elements, the dates and costs defined in the individual activities
are totaled up (aggregated) at the WBS level and can be evaluated. True or false - correct answer -True
What are some of the trends driving the need for a re-engineered business suite built for the digital? (3
correct)
A. Massive increase in device connectivity
B. Business users are taking on more technical IT Tasks
C. Increase in ownership of mobile devices
D. Adoption of cloud computing - correct answer -A. Massive increase in device connectivity
C. Increase in ownership of mobile devices
D. Adoption of cloud computing
Why was the application code completely re-written for SAP S/4HANA?(2 correct)
A. The optimized ABAP code that was developed for Suite on HANA would not work with SAP S/4HANA
B. To take advantage of the simpler data model
C. SAP S/4HANA is now built with Java
D. To ensure that the code is optimized for SAP HANA - correct answer -B. To take advantage of the
simpler data model
D. To ensure that the code is optimized for SAP HANA
Activity based costing occurs when costs are allocated based on work performed. which of the following
master data is required to perform an activity allocation? (4 correct)
A. Cost center
B. Activity type
C. Activity price
D. Primary cost element
E. Secondary cost element - correct answer -A. Cost center
B. Activity type
C. Activity price
E. Secondary cost element
,Of the steps listed below, which is the correct sequence of steps in the Purchase-to-Pay Business
Process?
1. Determination of Requirements
2. Source of supply determination
3. Vendor Selection
4. Purchase order handling
5. Purchase order monitoring
6. Goods reciept
7. Invoice verification
8. Handling of payments
A. 2,4,3,2,6,7,
B. 2,3,6,7,8
C. 5,4,3,6,7,8
D. 1,2,3,4,6
E. 1,4,6,7,8 - correct answer -D. 1,2,3,4,6
The purchasing data of the material master is relevant at what organizational level? ( 1 correct answer)
A. company code
B. Client
C. Storage location
D. Plant
E. Purchasing organization - correct answer -d. Plant
Your company has agreed tom purchase materials from a new supplier. Master data must be created for
this new Business Partner; this master data is relevant to which of the following roles?
A. General Role data relevant at the client level
B. General Role data relevant at the purchasing Organization level
, C. FI Vendor Role data relevant for the purchasing Organization level
D. Fi vendor Role data relevant for the company code
E. Supplier Role data relevant for the purchasing organization - correct answer -A. General Role data
relevant at the client level
D. Fi vendor Role data relevant for the company code
E. Supplier Role data relevant for the purchasing organization
Which of the following master data are defined at the Company Code level?
A. control data
B. Bank information
C. Account Management Data
D. Correspondance
E. Partner roles - correct answer -C. Account Management Data
D. Correspondance
Which of the following data are included in a purchasing info record?
A. Current and future prices
B. Last purchase Order number
C. Delivery Data
D. Payment terms
E. Receiving storage location - correct answer -A. Current and future prices
B. Last purchase Order number
C. Delivery Data
You are using the Project builder in SAP ERP Program and Project Management to edit your project.
Which of the following can be maintained in the project builder? ( 3 correct)
A. Activities
B. WBS Elements
C. PRT's