1. A project manager is assigned to a project with unclear scope and high uncertainty. Which development approach is MOST appropriate? A. Predictive B. Waterfall C. Agile D. Fixed-price Answer: C Agile is best suited for high-uncertainty, evolving requirements. 2. During sprint planning, a team member insists on adding extra features not in the backlog. What should the project manager do? A. Add the features if the team agrees B. Reject the idea C. Ask the product owner to evaluate and prioritize the items D. Immediately add to sprint Answer: C The product owner controls backlog content and prioritization.

Mostrar más Leer menos
Institución
PMP - Project Management Professional
Grado
PMP - Project Management Professional










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PMP - Project Management Professional
Grado
PMP - Project Management Professional

Información del documento

Subido en
21 de noviembre de 2025
Número de páginas
27
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

PMP PRACTICE EXAM with Complete Questions And
Correct Answers|Already Graded A+|Brand New
Version

1. A project manager is assigned to a project with unclear scope and high
uncertainty. Which development approach is MOST appropriate?
A. Predictive
B. Waterfall
C. Agile
D. Fixed-price
Answer: C
Agile is best suited for high-uncertainty, evolving requirements.


2. During sprint planning, a team member insists on adding extra features not
in the backlog. What should the project manager do?
A. Add the features if the team agrees
B. Reject the idea
C. Ask the product owner to evaluate and prioritize the items
D. Immediately add to sprint
Answer: C
The product owner controls backlog content and prioritization.


3. A key stakeholder keeps requesting changes but refuses to follow the
change control process. What should the PM do FIRST?
A. Escalate to sponsor
B. Implement the changes
C. Ignore the requests
D. Review the change control process with the stakeholder
Answer: D
Clarifying the process resolves most compliance issues.

,4. What is the primary purpose of a WBS?
A. Schedule development
B. Cost estimation
C. Scope decomposition
D. Risk identification
Answer: C
The WBS breaks the project scope into manageable components.


5. A PM is developing the stakeholder engagement plan. What should be
considered FIRST?
A. Communication channels
B. Project risks
C. Stakeholder analysis
D. Organizational structure
Answer: C
You must understand stakeholders before planning engagement.


6. A supplier notifies the PM of a two-week delivery delay. What should the
PM do NEXT?
A. Terminate the contract
B. Accept the delay
C. Evaluate the impact to schedule and project objectives
D. Inform the sponsor immediately
Answer: C
Assess impact before escalating or taking corrective action.


7. A project has a CPI of 0.72 and SPI of 0.95. What does this mean?
A. On budget, ahead of schedule
B. Under budget, behind schedule
C. Over budget, behind schedule
D. Over budget, ahead of schedule

, Answer: C
CPI < 1 = over budget; SPI < 1 = behind schedule.


8. Which document formally authorizes the project?
A. Business case
B. Scope statement
C. Project charter
D. Project plan
Answer: C
The charter gives authority to begin the project.


9. A team member is underperforming due to lack of training. What should
the PM do FIRST?
A. Remove them from the project
B. Escalate to HR
C. Provide or arrange training
D. Extend the schedule
Answer: C
Training is a PM responsibility and empowers the team.


10. Which conflict resolution technique is most effective for long-term
solutions?
A. Force
B. Withdraw
C. Smooth
D. Collaborate
Answer: D
Collaboration leads to win-win results and long-term resolution.


11. What is a primary output of Define Activities?
A. Activity list
B. Milestones
$22.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor
Seller avatar
lewizranking

Conoce al vendedor

Seller avatar
lewizranking Teachme2-tutor
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
Nuevo en Stuvia
Miembro desde
1 mes
Número de seguidores
0
Documentos
302
Última venta
-

0.0

0 reseñas

5
0
4
0
3
0
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes