100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

CAPM Questions with Answers (100% Correct Answers)

Puntuación
-
Vendido
-
Páginas
44
Grado
A+
Subido en
19-11-2025
Escrito en
2025/2026

CAPM Questions with Answers (100% Correct Answers)

Institución
CAPM
Grado
CAPM











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
CAPM
Grado
CAPM

Información del documento

Subido en
19 de noviembre de 2025
Número de páginas
44
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

1




CAPM Questions with Answers (100%
Correct Answers)
All of the following are parts of an effective change management plan except:

A. Procedures

B. Standards for Reports

C. Meetings

D. Lessons Learned Answer: D. Lessons Learned

The Customer wants to make a change to the product scope. The BEST thing
for a project manager to evaluate is:

A. Effect of the change of scope management

B. Effect of the change on the project scope

C. Effect of the change on the project schedule, cost, quality, risk, resources,
and customer satisfaction

D. Effect of the change on the project baselines Answer: C. Effect of the change
on the project schedule, cost, quality, risk, resources, and customer satisfaction

Which of the following BEST describes the difference between the Control
Scope process and the Perform Integrated Change Control process?

A. Control Scope focuses on making changes to the product scope, and
Perform Integrated Change Control focuses on making changes to integration.

B. Control Scope focuses on controlling the scope of the project, and Perform
Integrated Change control focuses on determining the impact of a change of
scope on time, cost, quality, risk, resources and customer satisfaction

C. Control Scope focuses on controlling the scope of the project, and Perform
Integrated Change Control focuses on making changes to integration

,2


D. Control Scope focuses on making changes to the product scope, and
Perform Integrated Change Control focuses on determining the impact of a
change to scope, time, cost, quality, risk, recourses and customer satisfaction.
Answer: B. Control Scope focuses on controlling the scope of the project, and
Perform Integrated Change control focuses on determining the impact of a
change of scope on time, cost, quality, risk, resources and customer satisfaction

Which of the following BEST describes when a project baseline should be
changed?

A. When a major delay occurs

B. When an official change is made

C. When a cost increase occurs

D. Changes should never be made to the baseline Answer: B. When an official
change is made

A company is making an effort to improve its project performance and create
historical records of its past projects. What is the BEST way to accomplish this?

A. Create project management plans

B. Create Lessons Learned

C. Create Network Diagrams

D. Create Status Reports Answer: B. Create Lessons Learned

If a project manager is concerned with gathering, integrating and disseminating
the outputs of all project managament processes, which of the following should
she concentrate on improving?

A. WBS

B. Communications Management Plan

C. Project Management Information System

,3


D. Project Scope Management Plan Answer: C. Project Management
information system

Which of the following BEST describes a project management plan?

A. The schedule, management plans, and budget

B. The projecxt managers's plan for managing and controlling work

C. The project charter, WBS, and project scope statement

D. A formal, approved document used to control the project Answer: D. A
formal, approved document used to control the project

You are beginning a new project that has been attempted, but unsuccessful,
several times in the past few years. Previous projects were cancelled because of
politics (differing views and direction by key stakeholders on the project). This
is an example of:

A. Stakeholder Analysis

B. Scope Management

C. Historical Information

D. Risk Identification Answer: C. Historical Information

When is it MOST important that integration be performed?

A: During Project Planning

B. During project executing

C. At key interface points

D. At the end of each project management process Answer: C. At key interface
points

Which of the following is included in the project management plan?

, 4


A. A risk management strategy

B. Work Package estimates

C. Detailed resource estimates

D. The business case for the project Answer: D. The business case for the
project

Which of the following is NOT included in the project management plan?

A. Change Management Plan

B. Integration Management Plan

C. Configuration Management Plan

D. Requirements Management Plan Answer: B. Integration Management Plan

When does the Monitor and Control Project Work process take place?

A. Throughout the project, from project initiating through project closing

B. During the monitoring and controlling process group

C. Primarily during the executing and monitoring and controlling processes

D. During project planning, executing, and monitoring and controlling
Answer: A. Throughout the project, from project initiating through project
closing

Which of the following BEST summarized what happens during the Perform
Integrated Change Control process?

A. Necessary changes to the project are identified and formally submitted as
change requests

B. CHange requests to the charter and project plan are implemented by the
project manager, without the need for further approvals.
$14.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Metric Yale School Of Medicine
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
92
Miembro desde
1 año
Número de seguidores
5
Documentos
13109
Última venta
1 semana hace

Welcome to Metric – Your Go-To Study Resource on Stuvia! At Metric, we believe studying should be smart, efficient, and effective. That’s why we offer high-quality, exam-ready study notes, summaries, and resources designed to help you understand key concepts faster and achieve better results. Whether you're cramming for finals, revising for a quiz, or looking to deepen your understanding, Metric provides content that’s clear, structured, and aligned with real course requirements. ✨ What you’ll find at Metric: ✔️ Accurate, in-depth summaries ✔️ Easy-to-follow formats for fast revision ✔️ Notes based on real syllabus & past exams ✔️ Regularly updated content you can trust Join hundreds of students who rely on Metric to study smarter—not harder. Browse the shop, grab what you need, and level up your academic game today!ades with Expert Academic Help

Lee mas Leer menos
3.0

12 reseñas

5
3
4
1
3
2
2
5
1
1

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes