All of the following are parts of an effective change management plan except:
A. Procedures
B. Standards for Reports
C. Meetings
D. Lessons Learned Answer: D. Lessons Learned
The Customer wants to make a change to the product scope. The BEST thing
for a project manager to evaluate is:
A. Effect of the change of scope management
B. Effect of the change on the project scope
C. Effect of the change on the project schedule, cost, quality, risk, resources,
and customer satisfaction
D. Effect of the change on the project baselines Answer: C. Effect of the change
on the project schedule, cost, quality, risk, resources, and customer satisfaction
Which of the following BEST describes the difference between the Control
Scope process and the Perform Integrated Change Control process?
A. Control Scope focuses on making changes to the product scope, and
Perform Integrated Change Control focuses on making changes to integration.
B. Control Scope focuses on controlling the scope of the project, and Perform
Integrated Change control focuses on determining the impact of a change of
scope on time, cost, quality, risk, resources and customer satisfaction
C. Control Scope focuses on controlling the scope of the project, and Perform
Integrated Change Control focuses on making changes to integration
,2
D. Control Scope focuses on making changes to the product scope, and
Perform Integrated Change Control focuses on determining the impact of a
change to scope, time, cost, quality, risk, recourses and customer satisfaction.
Answer: B. Control Scope focuses on controlling the scope of the project, and
Perform Integrated Change control focuses on determining the impact of a
change of scope on time, cost, quality, risk, resources and customer satisfaction
Which of the following BEST describes when a project baseline should be
changed?
A. When a major delay occurs
B. When an official change is made
C. When a cost increase occurs
D. Changes should never be made to the baseline Answer: B. When an official
change is made
A company is making an effort to improve its project performance and create
historical records of its past projects. What is the BEST way to accomplish this?
A. Create project management plans
B. Create Lessons Learned
C. Create Network Diagrams
D. Create Status Reports Answer: B. Create Lessons Learned
If a project manager is concerned with gathering, integrating and disseminating
the outputs of all project managament processes, which of the following should
she concentrate on improving?
A. WBS
B. Communications Management Plan
C. Project Management Information System
,3
D. Project Scope Management Plan Answer: C. Project Management
information system
Which of the following BEST describes a project management plan?
A. The schedule, management plans, and budget
B. The projecxt managers's plan for managing and controlling work
C. The project charter, WBS, and project scope statement
D. A formal, approved document used to control the project Answer: D. A
formal, approved document used to control the project
You are beginning a new project that has been attempted, but unsuccessful,
several times in the past few years. Previous projects were cancelled because of
politics (differing views and direction by key stakeholders on the project). This
is an example of:
A. Stakeholder Analysis
B. Scope Management
C. Historical Information
D. Risk Identification Answer: C. Historical Information
When is it MOST important that integration be performed?
A: During Project Planning
B. During project executing
C. At key interface points
D. At the end of each project management process Answer: C. At key interface
points
Which of the following is included in the project management plan?
, 4
A. A risk management strategy
B. Work Package estimates
C. Detailed resource estimates
D. The business case for the project Answer: D. The business case for the
project
Which of the following is NOT included in the project management plan?
A. Change Management Plan
B. Integration Management Plan
C. Configuration Management Plan
D. Requirements Management Plan Answer: B. Integration Management Plan
When does the Monitor and Control Project Work process take place?
A. Throughout the project, from project initiating through project closing
B. During the monitoring and controlling process group
C. Primarily during the executing and monitoring and controlling processes
D. During project planning, executing, and monitoring and controlling
Answer: A. Throughout the project, from project initiating through project
closing
Which of the following BEST summarized what happens during the Perform
Integrated Change Control process?
A. Necessary changes to the project are identified and formally submitted as
change requests
B. CHange requests to the charter and project plan are implemented by the
project manager, without the need for further approvals.