The process of establishing clear and achievable objectives, measuring their
achievement, and adjusting performance in accordance with the results of the
measurement is called Answer: Management by objectives
During the full life cycle of the project, a plot of the project's expected
expenditures will usually follow a characteristic S curve. This indicates that
Answer: the bulk of the project budget will be spent in the execution phase
n which project lifecycle phase would you expect to have the greatest influence
on overall project cost? Answer: concept
Requirement is Answer: Quantified and documented needs of stakeholders
Quantified and documented expectations of customer
Quantified and documented expectations of sponsor
(all the above)
TQM is Answer: Total Quality Management
A common approach to implementing a quality improvement program
Of the following, which describes Management Information Systems? Answer:
Software that an enterprise uses to support business and administrative
operations
The type of planning that is equated with more specific data or is detailed in
nature is called Answer: tactical
What are the different types of costs in Microsoft Project? Answer: Fixed Cost,
Cost Per Use, Standard Cost, Overtime Cost
,2
What is the name of PMI's Organization maturity model for project
management? Answer: OPM3
Which of the following is NOT a characteristic of a Project? Answer: It is
managed in strict accordance with the PMBOK guidelines
A group of related projects that are managed in a coordinated way that usually
includes an element of ongoing activity is called a: Answer: Program
Project constraint could be on Answer: cost
resources
schedule
(all of the above)
Which of the following is NOT true about Project Management Office (PMO)?
Answer: PMO is not involved in coordinating communication across projects
Projects require project management while operations require business process
management or operations management. Projects can intersect with operations
at various points during the product lifecycle. Which of the following is not a
stage to represent this? Answer: At each executing phase
Enterprise environmental factors refer to both internal and external
environmental factor that surround or influence a project's success. Of the
following, which is NOT an enterprise environmental factor Answer: historical
data
A person who is involved in or may be affected by the activities or anyone who
has something to gain or lose by the activity of the project is called a: Answer:
stakeholder
Large projects may be divided into smaller, more manageable components
known as, Answer: subprojects
, 3
A manager who manages a group of related projects is called a - Answer:
Program manager
Which of the following activity is conducted last as part of closing process
group Answer: customer satisfaction survey
In the PMBOK, each process is broken into - Answer: Inputs and Outputs
Tools and techniques
A stakeholder has the greatest ability to influence a project during - Answer:
Initiation and Planning
A Project Manager should support making changes during Execution - Answer:
When they are warranted and inline with the strategic goals of the organization
Conducting Lessons Learned is a critical part of - Answer: Closing
Of the following, which is not a process from the Planning Process Group?
Answer: Perform Quality Assurance
The Change Management Plan should be included in which of the following?
Answer: Project Management Plan
Who is a Project Initiator? Answer: A person or organization that has the
ability and authority to start the project
Who does the Project Integration? Answer: Project Manager
Which of the following is true about Project Plan ? Answer: Project Plan needs
to have the buy in of the entire project team
Which of the following statements is MOST True? Answer: The project charter
names and authorizes the project manager
Which of the following may NOT be included in the Project Management
Plan? Answer: Performance measurement report