CAPM Final Test Questions with Answers
(100% Correct Answers)
What is the key benefit of the Closing Process Group? Answer: Phases,
projects, and contracts are closed out appropriately
All of the following are true about the statement of work (SOW) for a
procurement EXCEPT: Answer: It can be ambiguous or incomplete for future
negotiations
Which of the following includes all costs incurred over the life of the product by
investment in preventing non conformance to requirements, appraisal of the
product or service for conformance to requirements, and failure to meet
requirements? Answer: Cost of Quality (COQ)
Project Scope Management includes which of the following? Answer: Processes
required to ensure that the project includes all the work required -and only the
work- required to complete the project successfully
The collection of generally sequential and sometimes overlapping project
phases, whose name and number are determined by the management and
control the needs of the organizations or organizations involved in the project,
is known as the: Answer: Project life cycle
What tasks should be part of the scope management plan? Answer: Define a
strategy for handling scope change requests and create a work breakdown
structure (WBS)
Which of the following are considerations for the tailoring for project schedule
management? Answer: Life Cycle approach, resource availability, and project
dimensions
The cost management plan has all of the following characteristics EXCEPT:
Answer: It is based on project cost estimates and is seperate from the project
management plan
,2
Your sponsor specifies that there is no additional money in the budget for your
project and asks you to complete the project at the original budget at
completion (BAC). To achieve that goal, you and your team must complete the
remaining work at the to-complete performance index (TCPI) of
BAC= 200
PV= 100
AC=120
EV= 80 Answer: 1.50
TCPI equation: Answer: (BAC - EV) / (BAC - AC)
which of the following most accurately describes the quantitative assessments
of the probable costs required to complete project work, as well as contingency
amounts to account for identified risks and management reserve to cover
unplanned work? Answer: Cost Estimates
When tailoring processes for Project Quality Management, you should
consider all these. Answer: Policy compliance and auditing
Stakeholder Engagement
Standards and regulatory compliance
Change requests are processed for review and disposition through the Perform
Integrated Change Control process and may include which of the following
types of change activities? Answer: Preventive action
What is a formal proposal to modify a document, deliverable, or baseline?
Answer: Change Request
, 3
Which of the following is a form of project life cycle that may also be referred
to as waterfall life cycle?
Project Life Cycle
Product Life Cycle
Predictive Life Cycle
Adaptive Life Cycle Answer: Predictive Life Cycle
Which project schedule model displays start and end dates, as well as expected
durations? Answer: Bar Charts
Which of the following tools and techniques of Conduct Procurement is a form
of communicating with users or potential users of a product, service, or result?
Advertising
Expert Judgement
Data Analysis
Bidder Conferences Answer: Expert Judgement