CAPM Exam Questions with Answers (100%
Correct Answers)
Cost Variance formula Answer: Earned Value (EV) - Actual Cost (AC)
What are the 6 constraints? Answer: Scope, Risk, Resources, Quality,
Schedule, Budget
Initiating (Process Group) Answer: Processes performed to define a new
PROJECT or a new PHASE of an existing project
Planning (Process Group) Answer: Processes performed to establish total scope
of effort, define and refine objectives, and develop a course of action to attain
the objectives
Executing (Process Group) Answer: Processes performed to complete the work
defined in the project management plan to satisfy objectives
Monitoring & Controlling (Process Group) Answer: Processes to track, review,
and orchestrate progress and performance of a project
How many processes are in EXECUTING? Answer: 8
How many processes are in PLANNING? Answer: 24
How many processes are in INITIATING? Answer: 2
How many processes are in CLOSING? Answer: 2
How many processes are in MONITORING & CONTROLLING? Answer: 11
What are INPUTS? Answer: Tools and Techniques you can use to DO the
process
What are OUTPUTS? Answer: One or more things you can GET as a
RESULT of doing the process
How many processes are there? Answer: 47
,2
How many knowledge areas are there? Answer: 10
What are the 10 knowledge areas? Answer: Integration, Scope, Time, Cost,
Quality, Human Resources, Communication, Risk, Procurement, Stakeholder
Closing (Process Group) Answer: Processes to conclude all activities across all
process groups of a project
Validate Scope: What process group? What knowledge area? Answer:
Monitoring & Controlling (PG)
Scope Management (KA)
Validate Scope: What Tools and Techniques? Answer: Inspection
Group Decision Making
Develop Project Charter: What process group? What knowledge area? Answer:
Initiating (PG)
Integration Management (KA)
Develop Project Charter: What Tools and Techniques? Answer: Expert
Judgement
Facilitation Techniques
Create WBS: What process group? What knowledge area? Answer: Planning
(PG)
Scope Management (KA)
Create WBS: What Tools and Techniques? Answer: Decomposition
Expert Judgement
Plan Scope Management: What process group? What knowledge area?
Answer: Planning (PG)
, 3
Scope Management (KA)
Plan Scope Management: What Tools and Techniques? Answer: Expert
Judgement
Meetings
Direct & Manage Project Work: What process group? What knowledge area?
Answer: Executing (PG)
Integration Management (KA)
Direct & Manage Project Work: What Tools and Techniques? Answer: Expert
Judgement
PMIS
Meetings
Monitor & Control Project Work: What process group? What knowledge area?
Answer: Monitoring and Controlling (PG)
Integration Management (KA)
Monitor & Control Project Work: What Tools and Techniques? Answer:
Expert Judgement
Analytical Techniques
PMIS
Meetings
Perform Integrated Change Control: What process group? What knowledge
area? Answer: Monitoring and Controlling (PG)
Integration Management (KA)