According to the standard weight table, what is the TOTAL weight of
the following quantities of bolts? - ANSWERS-1,472 Ibs
Which of the following documents are used for reviewing contract time
charges before clearing estimates for final payment? - ANSWERS-
Construction Diaries
It is usually necessary to measure items, which are to be paid for on a
lump sum or "plan quantity" basis. - ANSWERS-FALSE
On the transmittal letter, how should field books be listed? -
ANSWERS-Book number & description of contents
What is the rea of the sodded section shown below? - ANSWERS-
11,241 SY
When a pay item is based on truck capacity and side boards have been
added to the truck body, what should you submit with the final estimates
package? - ANSWERS-Sketches of truck measurements
END OF
PAGE 1
, FDOT FINAL LATEST
ESTIMATES - LEVEL
1
Examples of site source records include: - ANSWERS-Field books, tally
sheets asphalt reports, latitude & department
While on aa metric project, what method would be used to document
final measured items in the field for site source record documentation. -
ANSWERS-Use only metric measuring devices, no conversion is
allowed
What two types of Estimates are needed to pay for the work performed
by contractors? - ANSWERS-Final & Progress Monthly
In case of discrepancies among the contract documents, which document
takes the highest precedence? - ANSWERS-Special Provisions
Contractors Recieve progress payments on the basis of? - ANSWERS-
Monthly Progress Estimates
Which of the following sets forth the Department's methods and
procedures for preparing and checking final estimates? - ANSWERS-
Preparation and Documentation Manual (PDM)