ANSWERS LATEST UPDATE ALREADY GRADED A+
______ is mainly concerned with effectively integrating project
management process groups required to accomplish project objectives.
A. Scope management
B. Integration
C. Execution
D. Cost and budgeting - correct answer- B. Integration
_______ is the degree to which a set of inherent characteristics fulfill
requirements
A. Grade
B. Quality
C. Integrity
D. Par - correct answer- B. Quality
_______ states in detail what needs to be done.
A. Project verification
B. The project charter
C. The project scope statement
D. Work breakdown templates - correct answer- C. The project
scope statement
,________ involves planning and coordinating overlapping project
processes, phases, and activities
A. Scope management
B. Time management
C. Integration management
D. Scheduling management - correct answer- C. Integration
management
_________ management ensures the project includes all the specified
work required, and ONLY the specified work, which is necessary to
successfully complete the project.
A. Project
B. Scope
C. Control
D. Risk - correct answer- B. Scope
"Inspection" is an activity used in
A. processing the project management plan
B. updating work breakdown
C. validate scope
D. define scope. - correct answer- C. validate scope
, A governance framework includes
A. all of the below
B. policies
C. rules
D. norms - correct answer- A. all of the below
A project is said to be temporary because:
A. it has a short duration
B. it has a definite beginning and end
C. it has the potential to be a continuous and ongoing effort
D. its project team outlives it. - correct answer- B. it has a definite
beginning and end
All of the following are characteristics of management except
A. focus on the bottom line
B. do things right
C. innovate
D. accept status quo - correct answer- C. innovate
Develop schedule tools include:
A. critical diagram method
B. chain path method