WITH VERIFIED SOLUTIONS 100% CORRECT
A project has a To-Complete Performance Index (TCPI) = 1.25. Which of
the following statements are true (select 2) :
1. The estimated value of the remaining work exceeds the value of the
remaining project funds.
2. The project is forcasted to complete under budget
3. The project may complete on plan if performance levels improve
4. The project is currently behind schedule - correct answer- 1. The
estimated value of the remaining work exceeds the value of the
remaining project funds.
3. The project may complete on plan if performance levels improve
A project manager may utilize these skills to reduce tension and promote
cooperation when stressful situations arise among team members:
A. Emotional Intelligence
B. Servant Leadership
C. Transparency
D. Stewardship - correct answer- A. Emotional Intelligence
,A study that examines the viability of a potential recommendation to
address business needs is known as:
A. Exploratory testing
B. Gap analysis
C. Root cause analysis
D. Feasibility analysis - correct answer- D. Feasibility analysis
An activity has an early finish date of January 21 and a late finish date of
January 28. What can be said of this activity?
A. The activity is on a non-critical path
B. The activity has a lead
C. The activity has a lag
D. the activity is on the critical path - correct answer- A. The activity
is on a non-critical path
An agile framework that develops iteratively and builds incrementally,
thus utilizes MoSCoW for prioritizing work requirements, and
prototyping to engage stakeholders in early discovery is
A. DevOps (Software Development IT Operations)
, B. XP (Extreme Programming)
C. DSDM (Dynamic Systems Development Method)
D. SAFe (Scaled Agile Framework) - correct answer- C. DSDM
(Dynamic Systems Development Method)
An ERD (Entity Relationship Diagram) would use which of the following
relationships to depict a basketball team with one and only one head
coach?
A. Optional One
B. Optional Many
C. Mandatory One
D. Mandatory Many - correct answer- C. Mandatory One
Because of a delay in project activities, a key project resource now has
been assigned two concurrent project assignments. When asked by the
resource what to do, you should first:
A. Look at the critical path and total float available in these two
activities.
B. Reassign one of the activities to another member of the project team
C. Instruct the resource to just get it done.