A Project is a ____ One-time activity with tasks and a ________ __________ - Answer
-Unique, fixed, duration
Project Management.
A system that provides for the ____, ____, _____, and _____ of a unique one-time
activity, so as to complete the project on time, on budget, and safely, to a specified
quality with no ______. - Answer -Planning, Organizing, Directing, Controlling. Claims
3 important Project Manager skills - Answer -Technical, Thinking, Human Relations
What does a PM have to Manage? - Answer -L - Labor
M - Materials
E - Equipment
S - Subcontracts
O - Other
What is the most important meeting in Construction? - Answer -Pre Construction
What is a PM's responsibility for risk? (AIM) - Answer -Assess, Identify, Manage
what type of documents are there? - Answer -Plans and Specs
AIA Documents.
AIA 101 - Answer -Contract
AIA Documents
AIA 201 - Answer -General Conditions
AIA Documents
AIA 701 - Answer -Instructions to bidders
AIA Documents
AIA 703 - Answer -Schedule of Values
AIA Documents
AIA 704 - Answer -Certificate of Completion.
What does the Certificate of completion mean? - Answer -1. Starts warranty period
2. ends liquidated damages
CSI Division 01 - Answer -General Requirements
CSI Division 02 - Answer -Existing Conditions
A Project is a ____ One-time activity with tasks and a ________ __________ - Answer
-Unique, fixed, duration
Project Management.
A system that provides for the ____, ____, _____, and _____ of a unique one-time
activity, so as to complete the project on time, on budget, and safely, to a specified
quality with no ______. - Answer -Planning, Organizing, Directing, Controlling. Claims
3 important Project Manager skills - Answer -Technical, Thinking, Human Relations
What does a PM have to Manage? - Answer -L - Labor
M - Materials
E - Equipment
S - Subcontracts
O - Other
What is the most important meeting in Construction? - Answer -Pre Construction
What is a PM's responsibility for risk? (AIM) - Answer -Assess, Identify, Manage
what type of documents are there? - Answer -Plans and Specs
AIA Documents.
AIA 101 - Answer -Contract
AIA Documents
AIA 201 - Answer -General Conditions
AIA Documents
AIA 701 - Answer -Instructions to bidders
AIA Documents
AIA 703 - Answer -Schedule of Values
AIA Documents
AIA 704 - Answer -Certificate of Completion.
What does the Certificate of completion mean? - Answer -1. Starts warranty period
2. ends liquidated damages
CSI Division 01 - Answer -General Requirements
CSI Division 02 - Answer -Existing Conditions