100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

CAPM Exam Study 2025 Questions With Complete Solutions

Puntuación
-
Vendido
-
Páginas
51
Grado
A+
Subido en
12-11-2025
Escrito en
2025/2026

CAPM Exam Study 2025 Questions With Complete Solutions

Institución
CAPM
Grado
CAPM











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
CAPM
Grado
CAPM

Información del documento

Subido en
12 de noviembre de 2025
Número de páginas
51
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

CAPM Exam Study 2025 Questions With Complete
Solutions

A mobile device manufacturer is halfway through prototyping a
new product when the supplier who provides one of the raw
materials used to manufacture their device casings declares
bankruptcy and goes out of business. The team had not foreseen
this problem during project planning.
Which of the following best describes a process that may not
have been performed comprehensively in this scenario?
A
Perform qualitative risk analysis
B
Monitor risks
C
Identify risks
D
Plan risk management Correct Answers Correct answer:
Identify risks

The identify risks process is used to identify potential project
risks individually as well as overall risks to the project in
general. The characteristics of the risks are documented so that
they can be analyzed (perform qualitative and perform
quantitative risk analysis processes) and planned for (plan risk
responses). Without proper identification of risks before they are
realized, they cannot be planned for, and responses are often
pressured by time and cost constraints.

,Plan risk management is incorrect, as it refers to the process
when the methods of conducting risk management activities for
a project are determined.

Perform qualitative risk analysis is incorrect, as it prioritizes
individual risks for deeper analysis due to factors like
probability of occurrence and impact to the project.

Monitor risks is incorrect, as it tracks the implementation of the
planned risk management activities.

A project manager has been asked by a senior stakeholder to
implement some changes to the project. In evaluating the
situation and talking to the upper leadership team, the team
agreed to proceed forward with the processes to implement the
change. At what point should the project manager evaluate the
impact of a requested change?
A
First, before any other action is started
B
After the change request is approved
C
After they get the customer to buy in on the change
D
After they find a way to save time by implementing the change
Correct Answers Correct answer: First, before any other action
is started

The project manager should evaluate the impact of a requested
change before taking any other action. The project manager
should follow these steps regarding requested changes:

,Evaluate the impact
Create options
Get the change request approved
Get customer buy-in

After conducting a cost-benefit analysis, it is determined that the
project you are working on will increase company sales by 15%
over the next three years. The organization has set a goal to
increase sales by 12% within the next three years. This project
fits into what?
A
The company's business need for the project
B
The company's strategic plan
C
The product scope description
D
The project statement of work Correct Answers Correct answer:
The company's strategic plan

The strategic plan documents the organization's strategic vision,
goals, and objectives and may contain a high-level mission
statement. All projects should be aligned with their
organization's strategic plan. Strategic plan alignment ensures
that each project contributes to the overall objectives of the
organization.

In this case, the organization has announced it would like to see
a 12% increase in sales over the next three years, and
completing this project will exceed that organizational goal.

, Bai is the project manager in charge of a team very diverse in
skill sets and expertise. She works with the HR manager to add
each team member's newly acquired skills to their human
resource records. What process group will best identify where
the project manager is currently in?
A
Closing
B
Monitoring & Controlling
C
Planning
D
Executing Correct Answers Correct answer: Closing

The project manager is in the closing process group when they
are working with the HR manager to add the newly acquired
skills of each team member to the team members' human
resource records. Closing is those processes performed to
formally complete or close a project, phase, or contract.

At project or phase closure, the following may occur:

Obtain acceptance by the customer or sponsor to formally close
the project or phase
Conduct post-project or phase-end review
Record impacts of tailoring to any process
Document lessons learned
Apply appropriate updates to organizational process assets
Archive all relevant project documents in the Project
Management Information System (PMIS) to be used as
historical data
$21.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Classroom NURSING
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
4687
Miembro desde
3 año
Número de seguidores
3218
Documentos
51990
Última venta
18 horas hace
NURSING

Assignments, Case Studies, Research, Essay writing service, Questions and Answers, Discussions etc. for students who want to see results twice as fast. I have done papers of various topics and complexities. I am punctual and always submit work on-deadline. I write engaging and informative content on all subjects. Send me your research papers, case studies, psychology papers, etc, and I’ll do them to the best of my abilities. Writing is my passion when it comes to academic work. I’ve got a good sense of structure and enjoy finding interesting ways to deliver information in any given paper. I love impressing clients with my work, and I am very punctual about deadlines. Send me your assignment and I’ll take it to the next level. I strive for my content to be of the highest quality. Your wishes come first— send me your requirements and I’ll make a piece of work with fresh ideas, consistent structure, and following the academic formatting rules. For every student you refer to me with an order that is completed and paid transparently, I will do one assignment for you, free of charge!!!!!!!!!!!!

Lee mas Leer menos
4.0

1162 reseñas

5
612
4
213
3
190
2
39
1
108

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes