And Well Elaborated Solutions |Verified 100%
Correct|
According to NFPA 72, cellular transmission is a performance based technology
and as such _____?
A. Requires AHJ approval
B. Requires the use of a DACT
C. Requires a secondary means of transmission
D. Does not require a secondary communications path - answer -D. Does not
require a secondary communications path
NFPA 72 26.6.3.3
Consider the installation of a protected premises fire alarm system. All software
and firmware shall be protected against unauthorized access. Access by persons
who have are trained and authorized to either repair the control unit or to alter its
site specific data or operating system program, thereby changing its basic mode of
operation should be considered Access Level _____?
A. 4
B. 1
C. 2
D. 3 - answer -A. 4
NFPA 72 A.23.2.2.2
Consider the use of spot type smoke detectors at elevations above 3,000 feet above
sea level. This altitude may affect _____ detectors?
A. Projected beam
B. Photoelectric
, C. Air sampling
D. Ionization - answer -D. Ionization
NFPA 72 A.17.7.1.8
While testing a fire alarm system at a correctional facility, it is determined that the
general fire alarm signal requires human intervention to be initiated. This is
permitted using a _____ feature?
A. Pre signal
B. Positive alarm sequence
C. Manual initiation
D. Alarm verification - answer -A. Pre Signal
NFPA 72 23.8.1.1.2(3)(a)
Consider a 50′ x 50′ room with a 12′ ceiling. What is the minimum intensity
required for a ceiling mount strobe?
A. 85 cd
B. 110 cd
C. 80 cd
D. 95 cd - answer -D. 95 cd
NFPA 72 Table 18.5.5.1.1(b)
Consider a building with 4 floors and multiple basements. The recommended
coded signal designation for the 3rd floor is _____?
A. 3-2
B. 3-3
C. 2-2
D. 2-3 - answer -D. 2-3
NFPA 72 A.10.11.4