The offset of the jib has been changed D. Increase
from 25 degree to 15 degree. The capacity
of the jib will?
A. Stay the same
B. Decrease
C. Offset can't change
D. Increase
When lifting near capacity with a crawler, C. Over the side
the lowest ground pressure between
center pin and the load will be?
A. Over the front
B. Over the corner
C. Over the side
D. Over the rear
A Truck mounted crane will generally have B. Over the rear
a higher capacity over which quadrant?
A. Capacity is the same 360 degrees
B. Over the rear
C. Capacity is higher over the side
D. Over the front
When lifting from main boom with a 60' jib C. Erected jib
attached, a deduction must be made for?
A. Stowed jib
B. Fixed jib
C. Erected jib
D. Stored jib
,During Tandem lifts, neither crane should C. 75%
be loaded more than?
A. 50%
B. 65%
C. 75%
D. 80%
A chocker has a vertical hitch capacity of D. 6,000 lbs
6,000 lbs with a 5:1 safety factor. The actual
capacity is?
A. 30,000 lbs
B. 11,000 lbs
C. 3,000 lbs
D. 6,000 lbs
Mobile cranes are generally required to be B. 1%
level within?
A. 1 degree
B. 1%
C. 1'
D. 1"
A power line is rated 330kv, the closest a C. 170'
crane with 150' boom can get without a
spotter is?
A. 200'
B. 20'
C. 170'
D. 50'
ASME recommends, when hoisting A. No more than 100 f/m
personnel, line speeds of
A. No more than 100 f/m
B. No more than necessary
C. No more than 100 f/s
D. No speed recommendation
Rigging, custom hooks, clamps, spreader B. 125%
beams, etc. Shall be proof tested to ______ of
capacity
A. 100%
B. 125%
C. 110%
D. 115%
Blocking under outrigger pads should be B. Three times larger than the pad
what size?
A. Equal to the pad
B. Three times larger than the pad
C. Smaller than the pad
D. Five times larger than the pad
, When a crane is out of level, the capacity D. Long boom, Minimum radius
reduction is greatest in which
configuration?
A. Short boom, minimum radius
B. Long boom, maximum radius
C. Short boom, maximum radius
D. Long boom, minimum radius
The crane's anti-two block stopped D. Within 7 days
working. Per OSHA, how soon must it be
repaired?
A. Immediately
B. Within 30 days
C. Before end of shift
D. Within 7 days
Which is the OSHA criteria for removing A. Six random broken wires in one lay or three broken wires in one strand in one lay
running rope?
*Hoisting 6:3
A. Six random broken wires in one lay or *Rigging 10:5
three broken wires in one strand in one lay
B. 2 random broken wires in 6 diameters or
4 in 30 diameters
C. 3 random broken wires in 6 diameters or
in 6 in 12 diameters
D. 4 random broken wires in one lay or 10
broken wires in one strand
How far back from an excavation should a C. 1.5 to 1
crane be set up?
A. 1 to 1
B. 1 to 1.5
C. 1.5 to 1
D. 2 to 1
What is the margin for stability of a crawler A. 75%
crane?
A. 75%
B. 85%
C. 95%
D. 100%
Capacities above the bold line on a load D. Structural strength
chart are based on?
A. 85% of tipping capacity
B. Duty Cycle work
C. 75% of tipping capacity
D. Structural strength
OECP Test EXAM 2 2025 EXAM QUESTIONS
|FREQUENTLY TESTED QUESTIONS ||VERIFIED
SOLUTIONS (100% CORRECT)
Save
Students also studied
COSC 253 Exam 1 CON 367 Quizzes CM 413 - Exam #1 Forklift
Teacher 64 terms Teacher 57 terms Teacher 174 terms 25 terms
maxk85791 Preview Chelsea_Cloud67 Preview maxk85791 Preview Ele
The offset of the jib has been changed D. Increase
from 25 degree to 15 degree. The capacity
of the jib will?
A. Stay the same
B. Decrease
C. Offset can't change
D. Increase
When lifting near capacity with a crawler, C. Over the side
the lowest ground pressure between
center pin and the load will be?
A. Over the front
B. Over the corner
C. Over the side
D. Over the rear
A Truck mounted crane will generally have B. Over the rear
a higher capacity over which quadrant?
A. Capacity is the same 360 degrees
B. Over the rear
C. Capacity is higher over the side
D. Over the front
When lifting from main boom with a 60' jib C. Erected jib
attached, a deduction must be made for?
A. Stowed jib
B. Fixed jib
C. Erected jib
D. Stored jib
,During Tandem lifts, neither crane should C. 75%
be loaded more than?
A. 50%
B. 65%
C. 75%
D. 80%
A chocker has a vertical hitch capacity of D. 6,000 lbs
6,000 lbs with a 5:1 safety factor. The actual
capacity is?
A. 30,000 lbs
B. 11,000 lbs
C. 3,000 lbs
D. 6,000 lbs
Mobile cranes are generally required to be B. 1%
level within?
A. 1 degree
B. 1%
C. 1'
D. 1"
A power line is rated 330kv, the closest a C. 170'
crane with 150' boom can get without a
spotter is?
A. 200'
B. 20'
C. 170'
D. 50'
ASME recommends, when hoisting A. No more than 100 f/m
personnel, line speeds of
A. No more than 100 f/m
B. No more than necessary
C. No more than 100 f/s
D. No speed recommendation
Rigging, custom hooks, clamps, spreader B. 125%
beams, etc. Shall be proof tested to ______ of
capacity
A. 100%
B. 125%
C. 110%
D. 115%
Blocking under outrigger pads should be B. Three times larger than the pad
what size?
A. Equal to the pad
B. Three times larger than the pad
C. Smaller than the pad
D. Five times larger than the pad
, When a crane is out of level, the capacity D. Long boom, Minimum radius
reduction is greatest in which
configuration?
A. Short boom, minimum radius
B. Long boom, maximum radius
C. Short boom, maximum radius
D. Long boom, minimum radius
The crane's anti-two block stopped D. Within 7 days
working. Per OSHA, how soon must it be
repaired?
A. Immediately
B. Within 30 days
C. Before end of shift
D. Within 7 days
Which is the OSHA criteria for removing A. Six random broken wires in one lay or three broken wires in one strand in one lay
running rope?
*Hoisting 6:3
A. Six random broken wires in one lay or *Rigging 10:5
three broken wires in one strand in one lay
B. 2 random broken wires in 6 diameters or
4 in 30 diameters
C. 3 random broken wires in 6 diameters or
in 6 in 12 diameters
D. 4 random broken wires in one lay or 10
broken wires in one strand
How far back from an excavation should a C. 1.5 to 1
crane be set up?
A. 1 to 1
B. 1 to 1.5
C. 1.5 to 1
D. 2 to 1
What is the margin for stability of a crawler A. 75%
crane?
A. 75%
B. 85%
C. 95%
D. 100%
Capacities above the bold line on a load D. Structural strength
chart are based on?
A. 85% of tipping capacity
B. Duty Cycle work
C. 75% of tipping capacity