Project Management C722, Pre-Assessment QUESTIONS WITH ANSWERS

Puntuación
-
Vendido
-
Páginas
32
Grado
A+
Subido en
09-11-2025
Escrito en
2025/2026

Project Management C722, Pre-Assessment QUESTIONS WITH ANSWERS

Institución
Grado











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Grado

Información del documento

Subido en
9 de noviembre de 2025
Número de páginas
32
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

Project Management C722, Pre- |\ |\ |\




Assessment QUESTIONS WITH |\ |\ |\




ANSWERS

A project was authorized as an operational necessity to repair a
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


design flaw in the date field on a computer system that
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


constrains the year number to two digits instead of permitting
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


the year to be indicated with four digits. During execution of the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


activity concerned with identifying the affected software, five
|\ |\ |\ |\ |\ |\ |\ |\


relevant software modules were discovered that had not been
|\ |\ |\ |\ |\ |\ |\ |\ |\


included in the scope baseline. The project team must adjust the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


baselines to include the omitted scope. |\ |\ |\ |\ |\




Which change management phase does this scenario describe?
|\ |\ |\ |\ |\ |\ |\




a) Preparing for the change
|\ |\ |\ |\




b) Managing the change
|\ |\ |\




c) Reinforcing the change
|\ |\ |\




d) Upgrading the change - CORRECT ANSWERS ✔✔a) Preparing
|\ |\ |\ |\ |\ |\ |\ |\ |\


for the change
|\ |\




A general contractor is managing a highway construction project
|\ |\ |\ |\ |\ |\ |\ |\ |\


that will repair a flood-damaged road. The Department of
|\ |\ |\ |\ |\ |\ |\ |\ |\


Transportation offered an incentive fee if the repairs are |\ |\ |\ |\ |\ |\ |\ |\ |\


completed early. Therefore, the project manager has established
|\ |\ |\ |\ |\ |\ |\ |\


a rewards and recognition program and has communicated this
|\ |\ |\ |\ |\ |\ |\ |\ |\


program to the project team member. The project's recognition
|\ |\ |\ |\ |\ |\ |\ |\ |\

,program will reward project team members who add value by
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


accelerating the project while maintaining its ability to deliver the |\ |\ |\ |\ |\ |\ |\ |\ |\


completed scope correctly.
|\ |\ |\




Which change management phase does this scenario describe?
|\ |\ |\ |\ |\ |\ |\




a) Preparing for the change
|\ |\ |\ |\




b) Managing the change
|\ |\ |\




c) Reinforcing the change
|\ |\ |\




d) Upgrading the change - CORRECT ANSWERS ✔✔c) Reinforcing
|\ |\ |\ |\ |\ |\ |\ |\ |\


the change |\




A general contractor is managing a construction project that will
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


add a new conference room to an existing office building. The
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


project was documented in a fixed-price contract that specified a
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


completion date. The contract includes a damages clause |\ |\ |\ |\ |\ |\ |\ |\


imposing a late completion penalty if the conference room is not
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


ready for use by the due date. One month into the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


implementation, the customer wants to modify the room's |\ |\ |\ |\ |\ |\ |\ |\


lighting equipment. The requested change will delay the project's
|\ |\ |\ |\ |\ |\ |\ |\


critical path by three months.
|\ |\ |\ |\ |\ |\




Which process should be used to maintain the existing baseline?
|\ |\ |\ |\ |\ |\ |\ |\ |\




a) Using a change management system to influence performance
|\ |\ |\ |\ |\ |\ |\ |\




b) Absorbing the change request in the baselines for time and
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


cost
c) Focusing on the original scope
|\ |\ |\ |\ |\

,d) Using the risk management system to process change
|\ |\ |\ |\ |\ |\ |\ |\ |\


requests - CORRECT ANSWERS ✔✔a) Using a change
|\ |\ |\ |\ |\ |\ |\ |\


management system to influence performance |\ |\ |\ |\




A general contractor from Germany is managing a construction
|\ |\ |\ |\ |\ |\ |\ |\ |\


project in Norway that will add a new conference room to an
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


existing office building. The project needs to collect requirements
|\ |\ |\ |\ |\ |\ |\ |\


from the client prior to developing plans to build the new
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


conference room. |\




Which two actions would prove useful to plan the project's
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


quality?


a) Defining traceable and verifiable requirements that can be
|\ |\ |\ |\ |\ |\ |\ |\ |\


validated at project closure |\ |\ |\




b) Establishing metrics that describe what to measure and how to
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


measure it
|\ |\




c) Using inventory to protect against defects during project
|\ |\ |\ |\ |\ |\ |\ |\ |\


implementation
d) Changing the work plan to account for the project
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


experiencing common variation |\ |\




e) Using slogans and numerical quotas to exhort resources to
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


work harder - CORRECT ANSWERS ✔✔a & b
|\ |\ |\ |\ |\ |\ |\




a) Defining traceable and verifiable requirements that can be
|\ |\ |\ |\ |\ |\ |\ |\ |\


validated at project closure |\ |\ |\




b) Establishing metrics that describe what to measure and how to
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


measure it
|\ |\

, What is the name for the closing task where all project activities
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


are reviewed to determine what went right and what went
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


wrong?


a) Closeout review
|\ |\




b) Lessons learned review
|\ |\ |\




c) Client deliverables review
|\ |\ |\




d) Project manager review - CORRECT ANSWERS ✔✔b) Lessons
|\ |\ |\ |\ |\ |\ |\ |\ |\


learned review |\




What is another name for lessons learned review that is often
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\


used by the military and other uniformed services?
|\ |\ |\ |\ |\ |\ |\




a) Rules of engagement
|\ |\ |\




b) Activity report
|\ |\




c) Protocol assessment
|\ |\




d) After action report - CORRECT ANSWERS ✔✔d) After action
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


report


The customer of a project validates that scope has been
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\


completed for the second of three segments of the project.
|\ |\ |\ |\ |\ |\ |\ |\ |\




Which closure practice does this describe?
|\ |\ |\ |\ |\




a) Iteration completion
|\ |\
$23.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
EXAMSTUDYPLUG Stanford University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
308
Miembro desde
3 año
Número de seguidores
107
Documentos
18149
Última venta
3 días hace
GRADE BUDDY

Welcome to My Page! Are you looking for high-quality study resources to ace your exams or better understand your coursework? You've come to the right place! I'm passionate about sharing my knowledge and helping students succeed academically. Here, you'll find a wide range of well-organized notes, study guides, and helpful materials across various subjects, including Maths ,nursig, Biology, History, etc.. Each resource is carefully crafted with detailed explanations, clear examples, and relevant key points to help simplify complex concepts. Whether you're preparing for a test, reviewing lectures, or need extra support, my resources are designed to make your learning experience smoother and more effective. Let me be a part of your academic journey, and feel free to reach out if you have any questions or need personalized assistance!

Lee mas Leer menos
4.5

230 reseñas

5
155
4
50
3
13
2
5
1
7

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes