100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

BICSI RTPM COMPREHENSIVE EXAM QUESTIONS AND ANSWERS GRADED A+

Puntuación
-
Vendido
-
Páginas
18
Grado
A+
Subido en
30-10-2025
Escrito en
2025/2026

BICSI RTPM COMPREHENSIVE EXAM QUESTIONS AND ANSWERS GRADED A+

Institución
BICSI RTPM
Grado
BICSI RTPM










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
BICSI RTPM
Grado
BICSI RTPM

Información del documento

Subido en
30 de octubre de 2025
Número de páginas
18
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

BICSI RTPM COMPREHENSIVE EXAM QUESTIONS AND
ANSWERS GRADED A+
✔✔Completing a SoW Includes - ✔✔Basic Planning
Outlining the SoW Process
Organizing the Project Team
Writing and Reviewing

✔✔Basic Planning of the SoW - ✔✔Answer the "why" and "what"

✔✔Outlining the SoW - ✔✔Outline the entire SoW; Develop outline to:
*Allow full attention to technical
*Aid achieving continuity
*Help guard against ommission
*Eliminate Redundant materials and work

✔✔What is the PM's main objective in developing a SoW - ✔✔Developing a SoW that
is:
Logical and Readable
Emphasizes most important elements
Conveys exactly what is required

✔✔If the SoW does not provide enough detail the PM should - ✔✔Submit an RFI

✔✔Are periodic progress reports considered deliverables? - ✔✔NO

✔✔SoW should specify - ✔✔The number of copies of reports and the person they
should be delivered
Any physical arrangements necessary to ensure the owner's capability to examine end
product

✔✔Developing a Safety Plan - ✔✔Each contractor should have an occupational safety
plan.

✔✔On a project where the PM is issuing only design documents safety can be -
✔✔Excluded

✔✔The purpose of Risk Management - ✔✔Determine potential risks
Identify characteristics that may have an impact

✔✔Risk - ✔✔Events or circumstance that affect plan/ scope of the project

✔✔Liability - ✔✔Events or circumstances that affect the succes of the project

,✔✔Risks can become liabilities if - ✔✔They are not effectively managed

✔✔Components of Risk Planning - ✔✔Probability and Impact

✔✔Risk Assessment - ✔✔Process of identifying and classifying risks to mitigate

✔✔How do you assess a risk - ✔✔Analysis: Probability/ Impact
Identify: What, when, how can go wrong
Mitigation :Tolerance/ Contingeny

✔✔Systematically identify risks by - ✔✔Lessons Learned
Previous data
Brainstorming / SWOT chart
Cause and Effect Diagram

✔✔Risk Identification Process - ✔✔Should be done with as many key individuals as
possible

✔✔Risk information is derived from - ✔✔Analysis of high level deliverables
Analysis of WBS and Network Diagram
Analysis of Change Request
Project Team Input
Stakeholders Input

✔✔Risk Triggers - ✔✔Events that warn of occurance of risks
These are determined during risk identification

✔✔Risk Analysis Methods - ✔✔Qualitative and Quantitative

✔✔Qualitative Risk Analysis - ✔✔Qualifies the expected impact of cost, time, quality
(Hi, Mid, Low)

✔✔Quantitative Risk Analysis - ✔✔measuring the probability and consequences of risks
as well as estimating their implications for the project objectives. Rank and multiply

✔✔Risk Severity Grid - ✔✔Captures Quantitative analysis, (time, cost, quality, risk
proximity)

✔✔Risk Planning Mitigation Techniques - ✔✔Avoidance
Sharing
Transference
Moderation
Acceptance

, ✔✔Stakeholder MGMT - ✔✔Each Stakeholder must be analyzed: how they affect/
affected by the project.
Stakeholders are given a rank based on their authority/ interest level

✔✔Developing an Organizational Breakdown Structure (OBS) - ✔✔Identify people and
organizations needed to complete the project
Shows responsibility for other team members, let's everyone know their role and
includes phone#, email, clients team

✔✔Work Breakdown Structure - ✔✔Must cover projects end product and:
Planning the project
Implementing the project
Closing out the project
Diagrammed as tree or outline structure
(Should be very specific)

✔✔Developing a schedule using PERT - ✔✔Network diagrams to identify predecessor
and successor relationships

✔✔What are the dependencies of PERT - ✔✔Finish - Start
Finish - Finish
Start - Finish
Start - Start

✔✔Analogus Estimates - ✔✔Based on similar work done in the past

✔✔Parametric Estimates - ✔✔dollar/ foot

✔✔Engineering Estimates - ✔✔Developed by client

✔✔Subcontractor Estimates - ✔✔Special tools and skills

✔✔Definitive Estimates - ✔✔Based on Materials and Labor

✔✔Bottom-Up Estimates - ✔✔Uses WBS Tasks

✔✔Pert Estimates - ✔✔(Optimistic + (Most Likely*4) + Pessimestic)/6

✔✔Four Versions of the Schedule Using the PERT Formula - ✔✔Optimistic View
Most Likely View
Pessimistic View
PERT View

✔✔Planned Value (PV) - ✔✔The authorized budget assigned to scheduled work.
$11.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
BOARDWALK Havard School
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
171
Miembro desde
1 año
Número de seguidores
6
Documentos
18402
Última venta
2 días hace
BOARDWALK ACADEMY

Ace Your Exams With Top Quality study Notes And Paper✅✅ ALL ACADEMIC MATERIALS AVAILABLE WITH US✅✅ LEAVE A REVIEW SO THAT WE CAN LOOK AND IMPROVE OUR MATERIALS.✅✅ WE ARE ALWAYS ONLINE AND AVAILABLE DONT HESITATE TO CONTACT US FOR SYUDY GUIDES!!✅✅ EVERYTHING IS GRADED A+✅✅ COLOUR YOUR GRADES WITH US , WE ARE HERE TO HELP YOU DONT BE RELACTANT TO REACH US

3.6

31 reseñas

5
12
4
6
3
7
2
0
1
6

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes