100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

Stationary Engineer Electric Exam Study Guide – 2025 Questions, Answers & Practice Test Preparation

Puntuación
-
Vendido
1
Páginas
41
Grado
A+
Subido en
24-10-2025
Escrito en
2025/2026

stationary engineer electric exam, stationary engineer electrical test questions, power plant engineer exam prep, electrical maintenance certification exam, stationary engineer license practice test, NEC code exam questions and answers, electrician stationary engineer study guide, stationary engineer exam 2025 PDF, power systems and controls test bank, building systems engineer exam preparationDownload the Stationary Engineer Electric Exam Study Guide (2025 Edition) featuring comprehensive questions, accurate answers, and detailed explanations to help you master electrical systems for building and plant operations. This exam prep file includes practice tests on motors, transformers, control circuits, electrical safety, and power distribution, tailored for stationary engineers, electricians, and maintenance professionals. This guide supports preparation for licensing and certification exams, offering real-world examples, troubleshooting scenarios, and NEC-based references to ensure success on your next electric or stationary engineer qualification test.

Mostrar más Leer menos
Institución
STATIONARY ENGINEER ELECTRIC
Grado
STATIONARY ENGINEER ELECTRIC











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
STATIONARY ENGINEER ELECTRIC
Grado
STATIONARY ENGINEER ELECTRIC

Información del documento

Subido en
24 de octubre de 2025
Número de páginas
41
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

STATIONARY ENGINEER ELECTRIC EXAM | QUESTIONS AND
ANSWERS | VERIFIED ANSWERS (100% CORRECT) | LATEST EXAM
UPDATE




High pressure steam boilers generally operate at pressures
A. above 15 psi and over 6 boiler horsepower.
B. below 15 psi and over 8 boiler horsepower.
C. above 250 psi and over 6 boiler horsepower.
D. at 212 psi and over 8 boiler horsepower. - CORRECT ANSWER- A. above
15 psi and over 6 boiler horsepower.


Pressure gauges should never have a range less than
A. half the safety valve set pressure.
B. double the safety valve set pressure.
C. 3/4 times the safety valve set pressure.
D. 1 1/2 times the safety valve set pressure. - CORRECT ANSWER- D. 1 1/2
times the safety valve set pressure.


After water is blown out of a siphon, why should live steam never be allowed to
enter a Bourdon tube?
A. The steam will rupture the siphon tube.
B. Combustion gases will mix with the steam.
C. Live steam will damage the pressure gauge.
D. The water level gauge will be damaged or destroyed. - CORRECT
ANSWER- C. Live steam will damage the pressure gauge.


All of the following are essential to maintain the proper fuel oil pressure with
fuel oil accessories EXCEPT
A. achieving the right flow of fuel.

,B. proper atomization of the fuel oil.
C. heating fuel oil to the correct temperature.
D. obtaining the correct difference in pressure inside and outside the boiler. -
CORRECT ANSWER- D. obtaining the correct difference in pressure inside
and outside the boiler.


Which of the following could be dangerous to safe operation of a low pressure
boiler?
A. Adding water to an operating boiler when the water level cannot be seen in
the gauge glass tube.
B. Opening the blowdown valve at the bottom of the water gauge glass before
making a water level reading.
C. Checking the water level using the try cocks valves when the line to the glass
gauge tube is clogged.
D. Opening the water column blowdown valve every day. - CORRECT
ANSWER- A. Adding water to an operating boiler when the water level cannot
be seen in the gauge glass tube.


Which of the following is best if a low-pressure boiler does not have an air
vent?
A. Vent the boiler with the try cocks.
B. Vent the boiler with the safety valve.
C. Vent the boiler with the fusible plug.
D. Vent the boiler with the blowdown line. - CORRECT ANSWER- A. Vent
the boiler with the try cocks.


What is the purpose of an evaporation test on a low pressure boiler?
A. To test the water column
B. To test the bottom blowdown valve
C. To test the steam pressure safety valve

,D. To test the low water cutoff control. - CORRECT ANSWER- D. To test the
low water cutoff control.


Following flame failure, controls must de-energize fuel and ignition circuits
A. within 4 seconds.
B. within 6 seconds.
C. within 10 seconds.
D. within 15 seconds. - CORRECT ANSWER- A. within 4 seconds.


How can an operator prevent damage to the tubes while using a cleaner to
remove scale from boiler tubes?
A. Never use a chemical cleaning procedure.
B. Never use cleaning water under pressure.
C. Never allow the cleaner to stay in one place.
D. Never clean the tubes more often than every six months. - CORRECT
ANSWER- C. Never allow the cleaner to stay in one place.


In a steam boiler, which of the following should never be placed between the
safety relief valve and the boiler?
A. A steam trap
B. A shut-off valve
C. An air eliminator
D. A discharge pipe - CORRECT ANSWER- B. A shut-off valve


Which of these should be used on live electrical fires?
A. Class D extinguishers
B. Class C extinguishers
C. Class B extinguishers
D. Class A extinguishers - CORRECT ANSWER- B. Class C extinguishers

, If certain grades of fuel oil are not preheated properly, they may cause
A. higher temperatures in the furnace.
B. back pressure and leaks in the fuel lines.
C. poor combustion and high fuel consumption.
D. increased pressure and dangerous levels of steam. - CORRECT ANSWER-
C. poor combustion and high fuel consumption.


The furnace is almost always in a ___________ pressure.


Negative
Positive - CORRECT ANSWER- Negative


In an open feedwater heater or de-aerating feedwater tank, a clogged vent line
will _______ air/non-condensables in feedwater.


Increase
Decrease - CORRECT ANSWER- Increase


Reciprocating pump- rated by diameter of piston. 4x2x4 pump. The first number
is the diameter of the ___________. The second number is the diameter of the
______. The third number is the length of ________. - CORRECT ANSWER-
steam piston, water piston, stroke


Suction valve on reciprocating pump allows water into the ______ and keeps it
from backing up into the ______ line. If suction water is too hot the pump will
become steam bound. - CORRECT ANSWER- cylinder, suction


Horizontal split case centrifugal pump- center eye of impeller is ________
suction pressure. _________ is the formation and collapse of vapor bubbles
Gratis
Accede al documento completo:
Descarga

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor
Seller avatar
completeguide

Conoce al vendedor

Seller avatar
completeguide Abraham Lincoln University, School Of Law
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
8
Miembro desde
4 meses
Número de seguidores
0
Documentos
113
Última venta
1 mes hace

0.0

0 reseñas

5
0
4
0
3
0
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes