Which clause is related to Acquisition?
,,,,Answer,,,,,52.215 - Instructions to Offerors - Competitive
Acquistion
What is considered a contract action?
,,,,Answer,,,,,Contract action means any oral or written action that
results in the purchase, rent, or lease of supplies or equipment,
services, or construction.
What is latent defect?
,,,,Answer,,,,,is one that is not readily noticeable upon reasonable
inspection at the time of acceptance.
Who accepts the burden of latent defect?
,,,,Answer,,,,,The burden is on the government to prove that defective
material and workmanship was the probable cause of product failure
or non-conformance.
Who can you submit a claim to?
,2|Page
,,,,Answer,,,,,Contractor claims are submitted to the KO
What is a claim?
,,,,Answer,,,,,a written demand or assertion by one of the contracting
parties seeking (i) payment of a specific sum of money, (ii) adjustment
or interpretation of contract terms, or (iii) other relief arising under or
relating to the contract.
When is written certification for a claim required?
,,,,Answer,,,,,When a claim exceeds $100,000, contractors must provide
the following written certification (FAR 33.207).
What are protests?
,,,,Answer,,,,,they provide offerors with a tool to challenge federal
contract award decisions.
Who do you file a protest with?
,,,,Answer,,,,,The Government Accountability Office
There is a janitorial contract for 2.8 million dollars for the entire base.
What FAR part would you use?
,,,,Answer,,,,,Could be FAR Part 37 Service Contracting or Far Part
12 Acquisition of Commercial Products and Commercial Services
What common form do you use for a modification? ,,,,Answer,,,,,SF-30
, 3|Page
What FAR Part is Acquisition Planning? ,,,,Answer,,,,,FAR Part 7
What role does the Program Manager plan in Acquistion Planning?
,,,,Answer,,,,,The PM has overall responsibility of a contract
What is the KO's role in Acquisition Planning? ,,,,Answer,,,,,Ensures
plan is implemented and developed.
What are the three phases of a life cycle?
,,,,Answer,,,,,Pre-award Phase
Award Phase
Post-award phase
What are the two parts of the Pre-award phase?
,,,,Answer,,,,,Develop Solicitation
Develop offer
Who develops a solicitation? ,,,,Answer,,,,,The Government & The
Buyer.
Who prepares an offer? ,,,,Answer,,,,,The Contractor and the seller