and answers rated A+
A post award orientation aids both Government and contractor personnel to: - correct answer
✔✔ Achieve a clear and mutual understanding of all contract requirements and identify and
resolve potential problems
FAR 42.501
When late in paying an otherwise acceptable invoice, the Government will: - correct answer
✔✔ Pay an interest penalty
FAR 32.907(a)
When acquiring commercial items, quality assurance is primarily the responsibility of: - correct
answer ✔✔ The contractor
FAR 46.202-1
You have a requirement for an online subscription to Engineering News Record. The site owner
requires payment before they will provide the license code number to activate the annual
subscription. Which payment form is required? - correct answer ✔✔ An advance payment
FAR 32.102(a)
What agency does DoD typically delegate contract administrative functions for supply
contracts? - correct answer ✔✔ Defense Contract Management Agency
, FAR 42.201(b)
A purpose of a postaward orientation is to: - correct answer ✔✔ Achieve a clear and mutual
understanding of all contract requirements
42.501(a)
A contractor employee accidentally broke a test fixture that belongs to the Government and is
accountable to a Government contract. Generally speaking: - correct answer ✔✔ Contractors
are not held liable for loss of Government property
FAR 45.104
According to the FAR, the acquisition team: - correct answer ✔✔ Includes the contractor
FAR 1.102-3
With limited exceptions, a Contractor Performance Assessment Reporting System (CPARS)
report is required: - correct answer ✔✔ When the contract dollar value exceeds the simplified
acquisition threshold
FAR 42.1502(b)
To be determined responsible by a contracting officer, a prospective contractor must: - correct
answer ✔✔ Have adequate financial resources to perform the contract, or the ability to obtain
them