ISDS 3115 Exam 1 Questions and Answers Fully Solved Latest Version Shortening the project's duration by deleting unnecessary activities is called "project crashing" T or F - Answers False Which of the following statements regarding PERT analysis is true? A. The most likely time is equivalent to the expected activity time. B. Only critical activities contribute to the project variance. C. Each activity has two estimates of its duration. D. Project standard deviation is the sum of all critical activity standard deviations. E. Project variance is the sum of all activity variances. - Answers B. Only critical activities contribute to the project variance. An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 8. What is its expected activity time and variance? - Answers 3.67, 1 O=2 M=3 P=8 Duration = O + 4 x M + P Variance = ((P-O)/6)^2 Mean squared error and exponential smoothing are two measures of the overall error of a forecasting model. T or F - Answers False One use of short-range forecasts is to determine: A. facility location. B. job assignments. C. capital expenditures. D. planning for new products. E. research and development plans. - Answers B. job assignments Increasing the number of periods in a moving average will accomplish greater smoothing, but at the expense of: A. sensitivity to real changes in the data. Your answer is correct. B. stability. C. accuracy. D. manager understanding. E. All of the above are diminished when the number of periods increases. - Answers A. Sensitivity to real changes in the data A fundamental distinction between trend projection and linear regression is that: - Answers in trend projection the independent variable is time; in linear regression the independent variable need not be time, but can be any variable with explanatory power Which of the following is an example of a "hidden" production function? A. transplanting a liver B. manufacturing a television C. producing a computer D. assembling a motorcycle - Answers A. Transplanting a liver Which of the following OM decisions determines how a good or service is produced and commits management to specific technology, quality, human resources, and capital investment? A. human resources and job design B. managing quality C. process and capacity design D. design of goods and services - Answers C. Process and capacity design Which of the following organizations does NOT belong to the service sector? A. Southwest Airlines B. San Diego Zoo C. Ford Motor Company D. Costco - Answers C. Ford Motor Company Which one of the following statements is incorrect regarding globalization and globalization strategies? A. Globalization strategies could contribute to efficiency. B. Globalization strategies could simplify the operations manager's job C. Globalization means customers, talent, and suppliers are worldwide. D. Globalization strategies could add value to products and services. - Answers B. Globalization strategies could simplify the operations manager's job

Mostrar más Leer menos
Institución
ISDS 3115
Grado
ISDS 3115









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
ISDS 3115
Grado
ISDS 3115

Información del documento

Subido en
10 de septiembre de 2025
Número de páginas
12
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

ISDS 3115 Exam 1 Questions and Answers Fully Solved Latest Version 2025-2026

Shortening the project's duration by deleting unnecessary activities is called "project crashing" T
or F - Answers False

Which of the following statements regarding PERT analysis is true?

A. The most likely time is equivalent to the expected activity time.

B. Only critical activities contribute to the project variance.

C. Each activity has two estimates of its duration.

D. Project standard deviation is the sum of all critical activity standard deviations.

E. Project variance is the sum of all activity variances. - Answers B. Only critical activities
contribute to the project variance.

An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and
pessimistic = 8. What is its expected activity time and variance? - Answers 3.67, 1

O=2

M=3

P=8

Duration = O + 4 x M + P

Variance = ((P-O)/6)^2

Mean squared error and exponential smoothing are two measures of the overall error of a
forecasting model. T or F - Answers False

One use of short-range forecasts is to determine:

A. facility location.

B. job assignments.

C. capital expenditures.

D. planning for new products.

E. research and development plans. - Answers B. job assignments

Increasing the number of periods in a moving average will accomplish greater smoothing, but at
the expense of:

, A. sensitivity to real changes in the data.

Your answer is correct.

B. stability.

C. accuracy.

D. manager understanding.

E. All of the above are diminished when the number of periods increases. - Answers A.
Sensitivity to real changes in the data

A fundamental distinction between trend projection and linear regression is that: - Answers in
trend projection the independent variable is time; in linear regression the independent variable
need not be time, but can be any variable with explanatory power

Which of the following is an example of a "hidden" production function?

A. transplanting a liver

B. manufacturing a television

C. producing a computer

D. assembling a motorcycle - Answers A. Transplanting a liver

Which of the following OM decisions determines how a good or service is produced and
commits management to specific technology, quality, human resources, and capital investment?

A. human resources and job design

B. managing quality

C. process and capacity design

D. design of goods and services - Answers C. Process and capacity design

Which of the following organizations does NOT belong to the service sector?

A. Southwest Airlines

B. San Diego Zoo

C. Ford Motor Company

D. Costco - Answers C. Ford Motor Company

Which one of the following statements is incorrect regarding globalization and globalization
$10.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TutorJosh Chamberlain College Of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
361
Miembro desde
1 año
Número de seguidores
16
Documentos
29351
Última venta
16 horas hace
Tutor Joshua

Here You will find all Documents and Package Deals Offered By Tutor Joshua.

3.6

56 reseñas

5
19
4
15
3
12
2
0
1
10

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes