This document provides practice questions and answers for NJDEP Class A&B Underground Storage Tank (UST) Operator Training. It covers compliance requirements such as inspection frequency, release detection, spill and overfill protection, cathodic protection, secondary containment, site closure, and financial responsibility. The Q&A format makes it a practical study tool for exam preparation and regulatory compliance training in New Jersey

Vista previa del contenido

NJDEP UST Training for Class A&B
Operators


A Class A operator shall maintain the records of UST site inspections for a MINIMUM
of: - ANS - 3 years

A class B operator shall not be responsible for more than the following facilities: - ANS -
45 facilities

A leak should be suspected in a 1,560-gallon tank if the variation between the beginning
and ending manual tank gauging liquid level measurements exceeds the weekly
standard of X gallons. X is: - ANS - 26 gallons

A manual tank gauge stick must be marked to the nearest: - ANS - 1/8 inch

A suspected release must be confirmed to the DEQ/LARA within: - ANS - 7 days

An automatic tank gauge must be able to detect a leak of X gallons per hour. X is: -
ANS - 0.2 gallons per hour

Automatic line leak detector may be used only if the method detects X gallons per hour
at 10 pounds per square inch line pressure within one hour. X is: - ANS - 3 gallons per
hour

Automatic line leak detectors must be able to detect a leak of at least X gallons per hour
at a line pressure of 10 psi within one hour. X is: - ANS - 3 gallons per hour

Can an owner use pollution liability insurance as a means of financial responsibility? -
ANS - Yes

Check if the following statement is true or false: "A third party evaluation of a statistical
inventory reconciliation is good for any type of tank and product." - ANS - False

, If a facility has been determined by the DEQ inspector to be out of compliance with the
significant operational compliance requirements, the DEQ shall retrain: - ANS - The
class A operator of the facility.

If you have 100 or fewer tanks, financial responsibility is required in the aggregate
amount of: - ANS - $1 million

Line testing of piping shall be capable of detecting X gallons per hour leak rate at 1 1⁄2
times the operating pressure. X is: - ANS - 0.1 gallons/hour

Manual tank gauging can be used as the 'sole' means of leak detection for tanks that
are X gallons or less in capacity. X is: - ANS - 550 gallons

MUSTR requires that X soil borings be taken as close as practical to the bottom of the
UST, but no more than 5 feet away from the tank, nor more than 2 feet below the tank.
X is: - ANS - 2 soil borings

MUSTR requires what to happen with a UST before it is removed from the ground or
closed in place? - ANS - Is registered and all fees paid.

New owners of an existing UST system shall register the UST system with the
DEQ/LARA within what period from date of ownership? - ANS - 30 days

Petroleum marketers are required to have financial responsibility to cover X dollars per
occurrence. X is: - ANS - $1,000,000

Pressurized underground piping that routinely contains regulated substances shall be
monitored for releases in a manner that meets the following requirements: - ANS -
Both A and B: A. Be equipped with a line leak detector. B. Have an annual line tightness
test.

Product inventory control shall be conducted monthly to detect a release of not less
than X% of flow-through plus 130 gallons on a monthly basis. X is: - ANS - 1%

Records of tank and piping tightness testing should be maintained for: - ANS - 5 years

Release detection records of sampling, testing, or monitoring shall be maintained for: -
ANS - 2 years

Secondary containment is required for all of the following except: - ANS - Vent line

Información del documento

Subido en
9 de septiembre de 2025
Número de páginas
5
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$10.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
janenurse
4.1
(45)
Vendido
260
Seguidores
221
Artículos
2457
Última venta
2 meses hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes