Exam Questions and CORRECT Answers
Scope creep refers to: - CORRECT ANSWER - the tendency for project scope to keep
getting bigger and bigger.
A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the
total scope of the project. - CORRECT ANSWER - work breakdown structure
Scope refers to: - CORRECT ANSWER - the work involved in creating the products and
the processes used to create them.
_____ involves reviewing the project charter, requirements documents, and organizational
process assets to create a scope statement, adding more information as requirements are
developed and change requests are approved. - CORRECT ANSWER - Defining scope
The term ______ describes a product produced as part of a project. - CORRECT
ANSWER - deliverable
The _____ approach for constructing a WBS starts with the largest items of the project and
breaks them into subordinate items. - CORRECT ANSWER - top-down
In the _____ approach, team members first identify as many specific tasks related to the project
as possible and then aggregate the specific tasks and organize them into summary activities, or
higher levels in the WBS. - CORRECT ANSWER - bottom-up
The ______ documents how project needs will be analyzed, documented, and managed. -
CORRECT ANSWER - requirements management plan
A(n) ____ is a task at the lowest level of the WBS. - CORRECT ANSWER - work
package