Prevention Plan (SWPPP) UPDATED
ACTUAL Exam Questions and CORRECT
Answers
Purpose of a SWPPP - CORRECT ANSWER -The SWPPP documents how you will
comply with the CGP Permit for your site
The SWPPP must be developed prior to submittal of your NOI
The SWPPP must meet or exceed the DEP requirements found in the CGP Part 4, titled
"Stormwater Pollution Prevention Plan (SWPPP)"
*Now, let's go to the CGP in the Appendix and review PART IV.
What must the SWPPP Contain - CORRECT ANSWER -Stormwater Team
Contractors/Subcontractors
Site/Construction Activities
Description
Site Map
Non-stormwater Discharges
Dewatering Controls (if applicable)
, BMPs
Permanent stormwater
management controls
Inspections
Maintenance
Signed Certificates (contractors and subs)
What must the SWPPP Contain (Stormwater Team) - CORRECT ANSWER -•Identify the
people responsible for implementing the SWPPP (Name and Position)
Identify who or whom will be the Qualified Inspector(s) that will be conducting inspections
List their individual responsibilities on the Team in developing or implementing the SWPPP
What Must the SWPPP Contain (Contractor and Subcontractors) - CORRECT ANSWER -
For this section we want to list all contractors and subcontractors that will be disturbing the soil
during their construction activities, or possibly introducing a pollutant that could be picked up in
stormwater runoff - Roofers? Probably not. Painters? Maybe!
Identify the area(s) each group will be working in and responsibilities
All of the contractors and subcontractors listed must sign the certification in order to be covered
under this SWPPP and the CGP NOI.