Certified Associate in Project Management (CAPM) Exam Questions and Answers PMBOK defines a stakeholder as: - ANSWERS -Individuals, groups or organizations who may affect, be affected by, or perceive themselves to be affected by a decision, activity, or outcome of a project. The project manager and team should consider each process along with its inputs, tools and outputs. As a result, they should choose which are applicable. This effort is known as - ANSWERS -Tailoring In Initiating, a project charter is created. According to the PMBOK, which person or group may help write the charter? - ANSWERS -Project management team The Monitoring and Controlling Process Group involves: - ANSWERS -Tracking, reviewing, and orchestrating the progress of the project Much information is collected and distributed during the life of the project. Data that is collected form controlling processes and analyzed in context is called: - ANSWERS -Work performance information The project manager should perform the Initiating processes at the start of each phase in order to: - ANSWERS -Keep the project focused on the business need As Planning occurs, more and more is known about the project and the project management plan becomes increasingly detailed. This detailing is known specifically as: - ANSWERS -Progressive elaboration

Mostrar más Leer menos
Institución
Certified Associate In Project Management
Grado
Certified Associate in Project Management









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Certified Associate in Project Management
Grado
Certified Associate in Project Management

Información del documento

Subido en
12 de agosto de 2025
Número de páginas
6
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

Certified Associate in Project
Management (CAPM) Exam Questions
and Answers6

PMBOK defines a stakeholder as: - ANSWERS -Individuals, groups or organizations who may
affect, be affected by, or perceive themselves to be affected by a decision, activity, or outcome
of a project.



The project manager and team should consider each process along with its inputs, tools and
outputs. As a result, they should choose which are applicable. This effort is known as -
ANSWERS -Tailoring



In Initiating, a project charter is created. According to the PMBOK, which person or group may
help write the charter? - ANSWERS -Project management team



The Monitoring and Controlling Process Group involves: - ANSWERS -Tracking, reviewing, and
orchestrating the progress of the project



Much information is collected and distributed during the life of the project. Data that is
collected form controlling processes and analyzed in context is called: - ANSWERS -Work
performance information



The project manager should perform the Initiating processes at the start of each phase in order
to: - ANSWERS -Keep the project focused on the business need



As Planning occurs, more and more is known about the project and the project management
plan becomes increasingly detailed. This detailing is known specifically as: - ANSWERS -
Progressive elaboration

, The process group that involves coordinating people and resources, managing stakeholder
expectations and completing the work defined in the project management plan is known as: -
ANSWERS -Executing



The Process group that contains more than 50% of the processes is known as: - ANSWERS -
Planning



>Direct and Manage Project Work is the process of leading and performing the work defined in
the project management plan. There are several outputs from this process. The only one
defined as typically tangible components completed to meet the project objectives is: -
ANSWERS -Deliverables



In conjunction with the project manager, which person or group needs to address every process
and the project environment to determine the level of implementation for each process? -
ANSWERS -Project team



The key benefit of one of the Integration processes is that it allows stakeholders to understand
the current state of the project, the steps taken, budget, schedule, and scope forecasts. This
process is known as: - ANSWERS -Monitor and Control Project Work



The project manager should participate in the development of the project charter to better
understand the project requirements. Understanding these requirements will better allow for: -
ANSWERS -Efficient resource allocation to project activities



As a change control expert, you are asked to work on a plan that documents how changes will
be controlled and monitored on the project. Additionally you are told it will ultimately become
part of the project management plan. This document is known as a: - ANSWERS -Change
management plan
$9.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Bensuda Oxford University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
846
Miembro desde
3 año
Número de seguidores
445
Documentos
21415
Última venta
2 días hace
ECONOMICS,NURSING,BIOLOGY AND ALL REVISION MATERIALS

DEDICATED TO PROVIDE YOU WITH THE BEST LEARNING MATERIALS THAT WILL IMPROVE YOUR GRADES ,WELCOME TO ALIZGRADES AND LETS DO IT TOGETHER!!! GOODLUCK!!!!!!!

3.7

158 reseñas

5
74
4
24
3
25
2
11
1
24

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes