A contractor and owner agree to a price of $35,800 for a home improvement project and sign a contract. What is the maximum down payment that the contractor may require before starting work? A) up to 50 percent of the contract price B) $1,000 C) $3,580 D) $7,160 - Answer -B) $1,000

Mostrar más Leer menos
Institución
CSLB Law And Business
Grado
CSLB law and business









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
CSLB law and business
Grado
CSLB law and business

Información del documento

Subido en
10 de agosto de 2025
Número de páginas
8
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

CSLB LAW AND BUSINESS REVIEW QUESTIONS


Which of the following statements about advertising is correct?
A)An unlicensed contractor may advertise for jobs submitting an application for a
contractors license
B) Unlicensed contractors may advertise for jobs under $500 if the ads state they are
unlicensed.
C) A licensed general engineering or building may not advertise as a "general
contractor."
D) All of the above - Answer -B) Unlicensed contractors may advertise for jobs under
$500 if the ads state they are unlicensed.

Which of the following requires a contractors license?
A) A person who hires employees to build structures on his or her own property.
B) A person who installs satellite antenna systems on residences.
C) A person who only installs electric fire alarm systems.
D) A person who only installs security alarm systems. - Answer -C) A person who only
installs electric fire alarm systems.

A contractor must notify the Registrar in writing of a change of business address within
____ days.
A)15
B)20
C)60
D)90 - Answer -D)90

A contractor and owner agree to a price of $35,800 for a home improvement project and
sign a contract. What is the maximum down payment that the contractor may require
before starting work?
A) up to 50 percent of the contract price
B) $1,000
C) $3,580
D) $7,160 - Answer -B) $1,000

Home improvement contracts must include all of the following, except:
A) the name, address, and license number of the contractor
B) statement that the contractor has a workers' comp policy or is exempt
C) exact dates when work will begin and be completed
D) "Mechanics' Lien Warning" - Answer -C) Exact dates when work will begin and be
completed

A joint control is primarily a third party management of the:
A) safety equipment and procedures
B) job scheduling

, C) inspections by a building official
D) construction funds - Answer -D) Construction funds

If a contractor's bilingual salesperson makes a presentation to a customer in Spanish,
the home solicitation contract:
A) may be written in English if the contract is clear and legible.
B) must be signed by an english speaking representative of the customer.
C) must be in Spanish
D) must be notarized - Answer -C) must be in Spanish

The maximum time an owner has to cancel a home solicitation contract is:
A) 24hrs from midnight of the day the contract was signed
B) until midnight of the second business day after the day the contract was signed
C) until midnight of the third business day after the day the contract was signed
D) 7 days - Answer -C) until midnight of the third business day after the day the
contract was signed.

How many days does a contractor have to refund any payments from the date that a
home solicitation contract is canceled?
A) 10
B) 15
C) 20
D) 30 - Answer -A) 10

The contract price of a service and repair contract may not exceed:
A) $750
B) $1,000
C) $1,500
D) $5,000 - Answer -A)$750

For the majority of construction defects, what is the maximum time a homeowner has to
file a lawsuit after the original close of escrow?
A)2years
B)4years
C)10years
D)15years - Answer -C)10years

On a public works project if the subcontractors percentage of the total bid exceeds
_____ the prime contractor must include the subcontractor's name and address in the
bid.
A) 0.5%
B) 2%
C) 5%
D) 10% - Answer -A) 0.5%
$13.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
GEEKA YALA UNIVERSITY
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1998
Miembro desde
3 año
Número de seguidores
1444
Documentos
46889
Última venta
2 días hace

3.8

342 reseñas

5
170
4
61
3
44
2
16
1
51

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes