100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

FDOT Earthwork Level 1 EXAM PREP 2025/2026 COMPLETE QUESTIONS BANK AND CORRECT DETAILED ANSWERS WITH RATIONALES || 100% GUARANTEED PASS <RECENT VERSION>

Puntuación
-
Vendido
-
Páginas
23
Grado
A+
Subido en
06-08-2025
Escrito en
2025/2026

FDOT Earthwork Level 1 EXAM PREP 2025/2026 COMPLETE QUESTIONS BANK AND CORRECT DETAILED ANSWERS WITH RATIONALES || 100% GUARANTEED PASS &lt;RECENT VERSION&gt; 1. Basics covered in Level 1 - ANSWER Nuclear Testing Speedy Moisture Report Forms 2. Earthwork has to do with the roadway in what way? - ANSWER Earthwork is the excavation and placement of soils and materials supporting the proposed roadway. 3. In Earthwork what is a lift? - ANSWER 6" of compacted depth at full width 4. In Earthwork what is a Lot? - ANSWER A lot is 1 lift at 500 ft or within compacted area. Isolated compaction operations are separate lots. 5. Sampling at the roadway is done for - ANSWER Done for base, sub grade, and embankment. 6. Sampling is determined how - ANSWER generated with random numbers usually by a Verification Inspector 7. What is important about sampling at the roadway - ANSWER Minimum of three representative sample combined. 8. What is LIMS? - ANSWER Laboratory Info Management System 9. The proctor theory is when compaction is achieved how - ANSWER by inputting energy to expel air and water in the soil voids 10. Compaction causes - ANSWER An increase in unit weight, decrease in compressibility and permeability. 11. Determine the dry density by - ANSWER Taking the wet density / 1.(moisture) = dry density To the nearest 0.1pcf 12. To determine the percent maximum density - ANSWER Take the calculated dry density / the maximum density from proctor x 100 = % max density to the nearest whole percent 13. How often does the speedy and scale need to be calibrated - ANSWER every 6 months Scale verified daily by inspector 14. For a 20g and a 26g how much reagent do you use - ANSWER 20g - 2 scoops 26g - 3 scoops 15. Minimum mixing time for Coarse and Clay material - ANSWER Coarse - 1 minute Clay - 3 minutes 16. On limerock you use the what reading - ANSWER Direct Dial 17. If a dial reading exceeds 20% then you - ANSWER Re-run with half the sample (10 or 13) and perform the test normally and double the dial reading by 2 18. If a dial reads 0 or extremely low - ANSWER Re-run with double the sample (40 or 52) and perform the test and divide the dial reading by 2 19. If the speedy gets hot - ANSWER Let it cool in shade 20. If the speedy is cold - ANSWER &gt;50F disregard and retest 21. Retest speedy if material comes out - ANSWER in lumps after test 22. Reagent and the sample creates what gas - ANSWER Acetylene gas and a mild alkali, calcium hydroxide (lime) 23. All test data is recorded where - ANSWER Earthwork density report 24. QC density compare log in data is for - ANSWER Initial start up and standard counts 25. Use the water table sign on - ANSWER The graph plots using an upside down triangle with a ling under it and have it dated and signed 26. Earthwork is the construction work necessary to produce roadbeds of the proper: - grade -alignment -shape and density - all of the above - ANSWER - all of the above 27. which of the following does not need to be done before earthwork operations begin -removal of obstructions -compaction of embankements -installation of traffic control devices -clearing and grubbing - ANSWER -compaction of embankements 28. preconstruction conferences are - ANSWER required 29. personnel from the ___, ___, and ___ should be present at the preconstruction conference - ANSWER FDOT, contractor, and utilities 30. May other interested parties also attend the preconstruction conference? - ANSWER yes 31. Which of the following are usual topics of discussion at preconstruction conferences? The project plan and special provision requirements Lines of communication and traffic control The Contractor's work plan and schedule of operation All of the above - ANSWER All of the above 32. Who should you look to for information about the issues discussed at the preconstruction conference Project Engineer/Administrator

Mostrar más Leer menos
Institución
FDOT Earthwork
Grado
FDOT Earthwork










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
FDOT Earthwork
Grado
FDOT Earthwork

Información del documento

Subido en
6 de agosto de 2025
Número de páginas
23
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

FDOT Earthwork Level 1 EXAM PREP
2025/2026 COMPLETE QUESTIONS BANK AND
CORRECT DETAILED ANSWERS WITH
RATIONALES || 100% GUARANTEED PASS
<RECENT VERSION>



1. Basics covered in Level 1 - ANSWER ✔ Nuclear Testing
Speedy Moisture
Report Forms

2. Earthwork has to do with the roadway in what way? - ANSWER ✔
Earthwork is the excavation and placement of soils and materials
supporting the proposed roadway.

3. In Earthwork what is a lift? - ANSWER ✔ 6" of compacted depth
at full width

4. In Earthwork what is a Lot? - ANSWER ✔ A lot is 1 lift at 500 ft
or within compacted area. Isolated compaction operations are
separate lots.

5. Sampling at the roadway is done for - ANSWER ✔ Done for base,
sub grade, and embankment.

6. Sampling is determined how - ANSWER ✔ generated with
random numbers usually by a Verification Inspector

7. What is important about sampling at the roadway - ANSWER ✔
Minimum of three representative sample combined.

,8. What is LIMS? - ANSWER ✔ Laboratory Info Management
System

9. The proctor theory is when compaction is achieved how -
ANSWER ✔ by inputting energy to expel air and water in the soil
voids

10. Compaction causes - ANSWER ✔ An increase in unit
weight, decrease in compressibility and permeability.

11. Determine the dry density by - ANSWER ✔ Taking the wet
density / 1.(moisture) = dry density
To the nearest 0.1pcf

12. To determine the percent maximum density - ANSWER ✔
Take the
calculated dry density / the maximum density from proctor x 100 =
% max density to the nearest whole percent

13. How often does the speedy and scale need to be calibrated -
ANSWER ✔ every 6 months
Scale verified daily by inspector

14. For a 20g and a 26g how much reagent do you use -
ANSWER ✔ 20g - 2 scoops
26g - 3 scoops

15. Minimum mixing time for Coarse and Clay material -
ANSWER ✔ Coarse - 1 minute
Clay - 3 minutes

16. On limerock you use the what reading - ANSWER ✔ Direct
Dial

, 17. If a dial reading exceeds 20% then you - ANSWER ✔ Re-run
with half the sample (10 or 13) and perform the test normally and
double the dial reading by 2

18. If a dial reads 0 or extremely low - ANSWER ✔ Re-run with
double the sample (40 or 52) and perform the test and divide the
dial reading by 2

19. If the speedy gets hot - ANSWER ✔ Let it cool in shade

20. If the speedy is cold - ANSWER ✔ >50F disregard and retest

21. Retest speedy if material comes out - ANSWER ✔ in lumps
after test

22. Reagent and the sample creates what gas - ANSWER ✔
Acetylene gas and a mild alkali, calcium hydroxide (lime)

23. All test data is recorded where - ANSWER ✔ Earthwork
density report

24. QC density compare log in data is for - ANSWER ✔ Initial
start up and standard counts

25. Use the water table sign on - ANSWER ✔ The graph plots
using an upside down triangle with a ling under it and have it dated
and signed

26. Earthwork is the construction work necessary to produce
roadbeds of the proper:

- grade
$13.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
BenjaminsStudyHub Teachme2-tutor
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
14
Miembro desde
8 meses
Número de seguidores
0
Documentos
285
Última venta
1 semana hace
BENJAMIN STUDY HUB

Welcome to this platform! Here, you'll find a wide range of carefully curated study resources, including in-depth documents, all-inclusive bundles, and professionally designed flashcards—all provided by BenjaminsStudyHub. These materials are thoughtfully created to enhance your learning experience and help you prepare for exams with confidence and ease. I'm available to assist you with any academic questions or support you might need. Feel free to reach out—I'm always happy to help you succeed in your studies. Thank you for choosing these resources, and I wish you a productive and fulfilling learning journey!

Lee mas Leer menos
3.2

5 reseñas

5
0
4
2
3
2
2
1
1
0

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes