1. What will I do today to advance the Iteration goals?
Are there any impediments that will prevent the team from
meeting the Iteration goals?;
2. What is typically included in the definition of done for the team
increment? - correct answer -Stories are accepted by the
Product Owner
3. Which two views does the Iteration review provide into the
program? (Choose two.) - correct answer -How the team did on
the Iteration How the team is doing on the Program Increment
4. An Agile Team collects the Iteration Metrics they have agreed
upon during which part of the team retrospective? - correct
answer -During the quantitative part of the team retrospective
, Page | 2
5. Which statement is true about the PI Planning event? - correct
answer -It involves everyone in the program over a two-day
period
6. Which activity is key to successfully implementing the Scaled
Agile Framework? - correct answer -Use a cadence-based PI
Planning process
7. Which statement describes a cadence-based PI Planning
event? - correct answer -It is an all-hands, two-day event with
the goal to create alignment
8. What is an example of an ART event? - correct answer -Scrum
of scrums
9. What visibility should Scrum Masters provide during the Agile
Release Train Sync? - correct answer -Visibility into progress
and impediments