PJM Generator Operator Capacity Emergencies UPDATED ACTUAL Exam Questions and CORRECT Answers Unit Startup Notification Alert - CORRECT ANSWER -Place generating units into a state of readiness (able to be brought online with 48 hours); when a reliability assessment determines long lead time generation is needed for a future period; roughly 6 days prior to day needed Maximum Generation/Load Management Alert - CORRECT ANSWER -Issued 1 or more days prior to operating day in question; to provide early alert that system conditions may require Maximum Generation Emergency (forecasted operating reserve requirement is greater than scheduled operating reserve); set up Supplementary Status Report (but may not use till operating day is in effect)

Mostrar más Leer menos
Institución
PJM Generation
Grado
PJM Generation









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PJM Generation
Grado
PJM Generation

Información del documento

Subido en
26 de julio de 2025
Número de páginas
6
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

PJM Generator Operator Capacity
Emergencies UPDATED ACTUAL Exam
Questions and CORRECT Answers
Unit Startup Notification Alert - CORRECT ANSWER -Place generating units into a state
of readiness (able to be brought online with 48 hours); when a reliability assessment determines
long lead time generation is needed for a future period; roughly 6 days prior to day needed


Maximum Generation/Load Management Alert - CORRECT ANSWER -Issued 1 or more
days prior to operating day in question; to provide early alert that system conditions may require
Maximum Generation Emergency (forecasted operating reserve requirement is greater than
scheduled operating reserve); set up Supplementary Status Report (but may not use till operating
day is in effect)


Primary Reserve Alert - CORRECT ANSWER -To alert member of the anticipated
shortage of operating reserve capacity; when the estimated operating reserve is less than the
forecasted primary reserve requirement


What does the primary reserve consist of? - CORRECT ANSWER -Synchronized and
non-synchronized reserves that can be brought online within 10 minutes


Where can you view current reserve requirements on PJM.com? - CORRECT ANSWER -
Data Viewer Guest


Voltage Reduction Alert - CORRECT ANSWER -To alert members that a voltage
reduction action may be required in a future critical period; when the estimated operating reserve
capacity is less than the forecasted synchronized reserve requirement


What actions are required of members for Unit Startup Notification/Max Gen Alert/Primary
Reserve Alert? - CORRECT ANSWER -Notify all stations, management and key
personnel; review plans to determine if any maintenance or testing can be deferred or cancelled;
inform PJM of any environmentally restricted units considering the need to obtain a temporary
variance from environmental regulators for specific generators to avoid load shed

, What actions are required of members for Voltage Reduction Alert? - CORRECT
ANSWER -Notify all stations, management and key personnel; SOS members/PJM
consider the issuing of Public Appeals; marketers proceed on heightened awareness of possible
emergency purchases


During periods of reserve deficiencies, other measures must be taken to maintain system
reliability including: - CORRECT ANSWER -‒Loading generation that is restricted for
reasons other than cost
‒Recalling non-capacity backed off-system sales ‒Purchasing emergency energy from
participants / surrounding pools
‒Load relief measures


Actions taken prior to entering into capacity related emergency procedures: - CORRECT
ANSWER -‒Review weather projections, load forecasts, reserve projections and
generation performance
‒Ensure LMPs are reflective of system conditions
‒Curtail all non-Firm exports (issue EEA1 if not already done)
‒Dispatch may elect to implement an interchange cap to stabilize the amount of interchange
during peak hours to protect against volatility


Primary Reserve Requirement/Synchronized Reserve Requirement are what percentage of large
single contingencies? - CORRECT ANSWER -150% of largest single contingency; 100%
of largest single contingency


Primary Reserve Warning - CORRECT ANSWER -Primary Reserve is less than Primary
Reserve Requirement (150% of largest single contingency) but greater than Synchronized
Reserve Requirement (100% of largest single contingency)


Member actions during Primary Reserve Warning: - CORRECT ANSWER -Notify all key
personnel and stations; ensure all deferrable maintenance or testing is halted; prepare to load
primary reserve; marketers still remain aware of emergency purchase possibility; inform PJM of
environmentally restricted units
$11.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
MGRADES Stanford University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1053
Miembro desde
1 año
Número de seguidores
100
Documentos
68976
Última venta
2 horas hace
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

166 reseñas

5
72
4
30
3
42
2
8
1
14

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes